An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Globe, Arizona District Snow Effort Mobile Resource Management Joel Miller , John Wakefield, Tim Fox

  2. GLOBE District Mission Statement: To construct, maintain and manage the state transportation system in the Globe District, to meet or exceed the expectations of our customers. Snow Mission • Keep the roads open and safe during snow storms. • Clear the roads of snow efficiently and safely. • Maximize use of limited resources for winter storm events.

  3. Snowfall Distribution State of Arizona Globe District Snow Coverage

  4. Snow Removal Program - Globe 7 Departments (ORGS) 30 Plow Trucks 65 Operators 21 State Routes 2507 miles

  5. PRIORITY ROUTES

  6. Maintenance Expenditures - Globe Snow and Ice Control = 21 Percent!

  7. Challenges in Managing Snow Operations 1. Legal – Showing when & where we plowed and applied chemical. 2. Public Relations – Showing the public in real time, when & where we’ve plowed and applied chemical. 3. Reviewing our storm operation for improvements. 4. Maximum efficiency with our limited resources. 5. Storm scheduling issues – Crews, Plows, Routes, and Materials. 6. Operator safety – Many areas without radio coverage.

  8. Solution Mobile Resource Management

  9. MRM Definition Mobile – An “on-board”, near real-time solution Resource – Trucks, People, Data Management – Utilizing information collected above.

  10. MRM for Snow Operations Project will eventually deploy 30 MRM units with cellular based communication devices in plows across the Globe District in 2 phases. Key Goal: Determine potential value added for equipping entire ADOT snowplow fleet w/ MRM units. Duration 12 Month ATRC Funding $125,000 + Globe’s $60,000 Total Program $185,000

  11. MRM for Snow Operations Phase 1 • Consisted of FORCE America DATA Commander installations in 12 current trucks with existing SSC5100 controllers (COMPLETE) • Partnering with the Equipment Shop, installs and fabrication was performed internally producing $11,227 in labor cost savings. • Started 12-11-2007 ~ Finished 4-1-2008 • Total Labor hrs = 538.5 • Total Cost $ 34,544 • Avg Labor+Parts per - $2601 • Avg Labor per unit - $2080 • Avg Parts Cost per Unit - $520

  12. MRM for Snow Operations Phase 2 • Consist of FORCE America DATA Commander AND SSC5100 controller installations in 16 current trucks with existing Dickey-John and Raven controllers (31%) • 5 trucks complete - • Total Labor hrs = 453 • Total Cost $ 29,352

  13. Typical Work Report from storm activity

  14. ReportCommand - ForceAmericaGranular Report showing material application

  15. ReportCommand - ForceAmericaRouteReport distance traveled by route input on SSC5100

  16. Material Usage Report • Project Annual Cost Savings • $ 62,920.00 • Assumes Five month storm season • Assumes operators 30 min paperwork effort

  17. Thank You!