S TEPS IN THE D EVELOPMENT OF A D ETAILED E STIMATE

S TEPS IN THE D EVELOPMENT OF A D ETAILED E STIMATE. 1. Study project documents 2. Develop Work Breakdown Structure (WBS) and Cost Code 3. Determine quantity take off 4. Price materials, equipment and labor 5. Define work done by others and obtain quotations.

yul
Download Presentation

S TEPS IN THE D EVELOPMENT OF A D ETAILED E STIMATE

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. STEPSINTHE DEVELOPMENTOFA DETAILED ESTIMATE Prof. Awad S. Hanna

  2. 1. Study project documents 2. Develop Work Breakdown Structure (WBS) and Cost Code 3. Determine quantity take off 4. Price materials, equipment and labor 5. Define work done by others and obtain quotations Prof. Awad S. Hanna

  3. 6. Determine Job Overhead Cost • Temporary electric utilities • Shop or maintenance facility • Fuel for general job vehicles • Materials Handling and Storage • Material storage area & bins • Warehouse facility • Subcontracted Indirect Cost • Disposal services • Soil or rock borings • Laboratory tests • Soil samples • Rock samples • Concrete samples • Surveying service • CPM scheduling services • Job photographs • Models • Artist renderings • Bonds and Insurance • Performance bond • Builders rick Insurance • Contractor’s liability insurance • Permits • Building • Site improvement • Road or entrance • Additions for Remote Sites • Communications • Living quarters for workmen • Kitchen and food service • Entertainment • Transportation • Temporary power • Water supply • Waste disposal • Indirect Job Labor • Project manager and/or Superintendent • Project engineer • Draftsman • Timekeeper • Office manager and/or secretary • Safety engineer and/or first aid attendant • Watchmen • Indirect Job Equipment • Project manager’s vehicle • Pickup truck • Site maintenance • Site Facilities • Construction Sign • Job site fence • Construction access/entrance • Portable toilets • Office trailers: contractor’s,engineer’s, first aid, change room and lockers • Telephone service Prof. Awad S. Hanna

  4. 7. Determination of Markup • Markup is an allowance for: a. Home Office overhead b. Contingency c. Profit • Markup range from 5% to 20% of the total project costs Prof. Awad S. Hanna

  5. a. Home Office Overhead • Insurance • Company policies not chargeable to projects • Benefits • Pension & retirement program • Profit sharing & bonus plans • Health insurance plan • Transportation • Company aircraft • Company automobiles • Company trucks • Commercial travel • Marketing • Advertising • Estimating • Other promotional costs • Maintenance • Maintenance& overhaul, not just chargeable • Salaries • Executive staff • marketing staff • Accounting staff • Estimating staff • Legal staff • Support staff: clerical, data processing, etc. • Facilities • Office purchase or rental • Furniture purchase or rental • Data processing equipment • Utilities • Telephone, fax, etc. • Heating & air conditioning • Illumination • Water • Taxes • Company Income • Property Prof. Awad S. Hanna

  6. b. Contingency • To cover unexpected risk, error and omission, and contract risk Prof. Awad S. Hanna

  7. c. Profit • Profit varies from 1% to 10% or more • Factors affecting profit • Need for work • Contract type • Total bid value • Risk • Competition • Economic Condition Prof. Awad S. Hanna

  8. 8. Determination of Contract Bond Cost • The contract document usually requires as a minimum a “performance bond” and a “payment bond.” • Bond cost ranges from 0.5% to1% of the total contract price. Prof. Awad S. Hanna

  9. Example of Determining Total Contract Price • Assumptions 1. Sales Tax = 6% of Direct Material Costs 2. Job Overhead Labor Costs = 25% of Direct Labor Costs 3. Job Overhead Management Costs = 10% of Direct Labor Costs 4. Markup = 20% of Total Project Costs Office O.H. = 10% Contingency = 2% Profit = 8% 5. Bond = 0.5% of 1% of Total Project Costs Prof. Awad S. Hanna

  10. Example of Determining Total Contract Price (cont.) • Estimated Directed Job Costs 1. Direct Labor Costs $25,670 2. Direct Material Costs 15,000 3. Direct Equipment Costs 13,000 (Owning & Operating Costs) 4. Subcontract Costs 20,000 5. DIRECT COST SUBTOTAL $73,670 Prof. Awad S. Hanna

  11. Example of Determining Total Contract Price (cont.) • Job Overhead Costs 6. Sales Tax [6% of (2)] $ 900 7. Job O.H. Labor [25% of (1)] $ 6,418 8. Job O.H. Management $ 2,567 [10% of (1)] 9. Total Job Overhead Costs $ 9,885 10. Total Estimated Job Costs $ 83,555 [(5) + (9)] 11. Total Cost [(10) x 1.2] $ 100,266 12. Bond [0.005 x (11)] 501 13. TOTAL CONTRACT COST $ 100,767 [(11) + (12)] Prof. Awad S. Hanna

  12. Example of Determining Total Contract Price (cont.) TOTAL CONTRACT COST 100,767 Bid Factor = = = 1.368 14. Markup [(11) - (10)] $16,621 Breakdown of Markup 14a. Office O.H. [0.10 x (10)] $ 8,356 14b. Contingency [0.02 x (10)] 1,671 14c. Profit [0.08 x (10)] 6,684 73,670 DIRECT COST SUBTOTAL Prof. Awad S. Hanna

  13. Total Components of Cost within a bid Bid Price = markup Main Office Job Main Office Job + Project Cost Job indirects Direct costs Support structure Force account executed Overhead Subcontractors Subcontractors Salaries Testing Access road Project office Portable toilets Guard Work packages Work packages Training Office equip. Parking lot Etc. Janitors Support constr. Insurance Etc. Testing Etc. Labor Constr. Equip. Materials Installed equip. Prof. Awad S. Hanna