An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BNL report~the history of Run7 start up~ Yoshihide Nakamiya

  2. BBC hardware work • Interlock test • - one ADAM module was not worked -> replace it to a new module • - one thermocouple broke (S2-4) -> will fix after run7 • External charge scan • - Adc conversion factor (BbcCalib.adc) • - find one Adc to lost linearity (Adc[72]) -> replace QVC+ADC • Internal charge & timing scan • - Tdc conversion factor (BbcCalib.tdc0 & tdc1) • - one of test pulse injector was not worked (Adc[85]) • -> replace discriminator for Tdc0&Tdc1 • - Adc[126] was not worked properly • -> replace QVC+ADC for Adc[126] • Measurement of noise rate • - a few thousand Hz at most (th = 30 mV)

  3. Interlock test [結果] ZOOM 交換した ADAM ⇒Fixed! 壊れている熱電対  ⇒run7の後に修理

  4. External charge scan ~ After replacement ~ ~ Before replacement ~ We got proper gain curve for Adc[72] after replacement of two daughter cards (QVC+ADC).

  5. Internal charge & timing scan ~ Before replacement ~ ~ After replacement ~ • Adc[85] was fixed after replacement of discriminators Tdc0&Tdc1). • Adc[126] was fixed after replacement of two daughter cards (QVC+ADC).

  6. Calibrations and Time-in • Time-in • - Adjust global timing offset • ⇒position delay : 170 • fine delay (ch 7) : 60 • Pedestal scan • - Adc pedestal (BbcCalib.pedstal) • HV optimization • - magnetic field off • ⇒http://www.hepl.hiroshima-u.ac.jp/phx/bnl/pmt/ • Run7/070323/opHV_run7_bon_070323.pdf • - magnetic field on • ⇒http://www.hepl.hiroshima-u.ac.jp/phx/bnl/pmt/ • Run7/070402/opHV_run7_boff_070402.pdf • Gain calibration • - PMT gain (BbcCalib.pmtgain) • Slewing calibration • - slewing parameter (BbcCalib.slewpar0&slewpar1) • Update LUT&Data Base

  7. Time in V124 Blue Beam Sync -position delay : 170 -fine delay (ch 7) : 60 Global timing offset wasadjusted on v124. Collision events are in the middle of Tdc window.

  8. Pedestal scan run list ========================== Threshold of Tdc0 run # ========================== 5mV run226402 10mv run226403 20mv run226404 30mv run226405 15mv run226406 ========================== pedestal was extrapolated by using gain curve as a function of threshold.

  9. HV optimization <HV optimization criteria> BBC play a role of not only trigger but centrality determination. We have to optimize HV to satisfy both requirements. 1) Trigger : MIP peaks must not be cut off by threshold since BBC play a role as trigger. 2) Centrality : We must assure linearity of Centrality. We need to pay attention to overflow of Adc under high multiplicity environment like Au+Au collision. I consider these criteria, especially about PMTs which belongs to the inner ring.

  10. HV optimization : B ON Run 226332 Run 227016 HV was optimized ~30 V decrease Tdc<2600 Isolation cut Tdc<2600 Isolation cut Tdc<2600 Tdc<2600 overflow We optimized HV for B ON.

  11. HV optimization : B OFF Run 227702 Tdc<2600 Isolation cut Tdc<2600 We optimized HV for B OFF.

  12. Gain calibation Run 227016 (B ON) - tdc0 < 2600 - isolation cut Run 227702 (B OFF) - tdc0 < 2600 - isolation cut gain calibration was done.

  13. Slewing calibarion Run 227016 (B ON) Slewing correction Run 227702 (B OFF) Slewing correction slewing calibration was done.

  14. LUT and DataBase • LUT : We made LUT • ⇒ need z offset from DC guys to finalize it. • DB : version 4001 & 4002 were updated • ⇒ need z offset from DC guys to finalize it. We are waiting for getting z offset calculated by DC&PC.

  15. other problems, solutions, remaining tasks • Laser offset calculation • HV mainframe 16 • - problem 1 : HV module was tripped • - problem 2 : HV mainframe was tripped • ⇒ 1) fix 5 fans since 5 fans were not worked • 2) replace the HV mainframe 16 • Remaining tasks • - LUT will be updated (the final version) • - Data Base will be updated (ver 4001, ver4002) • ⇒We are waiting for getting z offset calculated by DC&PC in order to • finalize calibrations

  16. Laser offset calculation The special connector were attached in laser fiber of North-bottom. -Laser signal could get delayed. -Laser intensity could decrease.

  17. Laser offset calculation Affter correction Before correction - Delay depended on laser intensity were automatically fixed by slewing correction - Delay by connection of the connector were fixed by manually as shown above.

  18. Laser offset calculation Black : before correction Red : after correction We calculated Zvertex offset by laser after corrected systematical delay of North-Bottom.

  19. HV mainframe 16 : problem 1 <Symptom 2> 1) HV became Disable. for HV_BB_N-1 & HV_BB_N-1 2) Status indicator shows.. HV_BB_N-1 : 10 HV_BB_N-2 : 40 **status 10 means “Trip -- Violation of supply limits” I'm not sure for status 40

  20. HV mainframe 16 : problem 2 <Symptom 1> 1) HV mainframe looks like OFF but actually ON. 2) Measured voltage went to 0V. But HV is “Enable” for HV_BB_N-1 & HV_BB_N-1

  21. Slot 11 Slot 1 Slot 0 N1 N3 0 0 . . . . N4 N2 1 1 HV mainframe 16 : Solutions? • Cable N1 and N2 are separated. ⇒problem 1 was disappeared • Fix fans on the HV crate since 5 fans (total 12 fans) broke • HV mainframe 16 was replaced ⇒ problem 2 is not seen so far

  22. Remaining tasks <Remaining tasks> • LUT will be updated as the final version • Data Base will be updated (ver 4001, ver4002) We are waiting that DC guy’s work has finished for the final update.