150 likes | 359 Views
Welcome to the Glenn Highway MP 66.5-92 Public Open House. Glenn Highway Rehabilitation Milepost 66.5-92 Neal Christensen, Project Manager Federal Highway Administration (FHWA), Western Federal Lands Division (WFL) www.wfl.fhwa.dot.gov. Purpose of the Meeting.
E N D
Glenn Highway Rehabilitation • Milepost 66.5-92 • Neal Christensen, Project Manager • Federal Highway Administration (FHWA), Western Federal Lands Division (WFL) • www.wfl.fhwa.dot.gov
Purpose of the Meeting • Provide an overview of the: • Corridor project, MP 66.5-92 • Chickaloon Bridge replacement project • Long Lake design options • Answer questions and collect feedback
Project Area Map Chickaloon Bridge Long Lake Area
Purpose and Need • The purpose of this project is to enhance the safety of the highway and accommodate the anticipated traffic for the next 20 years. • This rehabilitation project will: • Preserve and extend the service life of the highway • Enhance safety • Provide climbing lanes • Provide rock fall mitigation
Environmental Assessment Work • 1993: an Environmental Assessment and Finding of No Significant Impactfor Glenn Highway MP 35-109 were approved • 1993 thru 2014: four NEPA Re-evaluations** completed for phased improvements to the Glenn Highway, including near the Palmer and Sutton areas, Pinochle Hill, Hicks Creek and Caribou Creek • 2014: NEPA Re-evaluations for the replacement of the Chickaloon Bridge and Glenn Highway between MP 66.5 and 92 • ** A NEPA Re-evaluation, often used in large multi-phased construction projects that occur over a number of years, examines potential changes in environmental impacts that may have occurred in a project area previously reviewed under NEPA.
Chickaloon Bridge • The Chickaloon Bridge is a priority due to low structural ratings of the deck and railing. • Repair costs for the bridge are high, and the lifespan of the repairs would be limited. • Replacing the bridge now will cost less in total than repairing the bridge and then replacing it in the near future.
Long Lake Area South Alignment
What’s Next? • Continue design on MP 66.5-92 corridor project • Final design on the Chickaloon bridge • Additional public events, dates to be determined
THANK YOU • Project team members are present to answer questions. • www.wfl.fhwa.dot.gov/projects/ak/glenn • Project Email Address:glennhighway@dot.govNeal Christensen, FHWA Project ManagerPhone: (360) 619-7780