Forestry Mowing. NASECA Feb 2014 1016-00-61. Forestry Mowing. Forestry Mowing. Total project included 1275 stations of clearing along IH 90/94 from Camp Douglas to Exit 85 (Wisconsin Dells) Various areas within this 30 mile stretch ranging from 2 stations to 42 stations in size.

zenia
Download Presentation

Forestry Mowing

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Forestry Mowing NASECA Feb 2014 1016-00-61

  2. Forestry Mowing

  3. Forestry Mowing • Total project included 1275 stations of clearing along IH 90/94 from Camp Douglas to Exit 85 (Wisconsin Dells) • Various areas within this 30 mile stretch ranging from 2 stations to 42 stations in size. • Lane closers allowed weekly 7pm Sunday to 10am Friday prior to Memorial Day and 7pm to 9am nightly after Memorial Day • Contract required stumps to be flush with the existing ground • Contractor salvaged saw logs reducing the amount of debris • 1275 stations of clearing completed in a little over 30 working days. NASECA Feb 2014 1016-00-61

  4. Forestry Mowing Good NASECA Feb 2014 1016-00-61

  5. Forestry Mowing Good NASECA Feb 2014 1016-00-61

  6. Forestry Mowing Good NASECA Feb 2014 1016-00-61

  7. Forestry Mowing Good NASECA Feb 2014 1016-00-61

  8. Forestry Mowing Good NASECA Feb 2014 1016-00-61

  9. Forestry Mowing Bad NASECA Feb 2014 1016-00-61

  10. Forestry Mowing Bad NASECA Feb 2014 1016-00-61

  11. Forestry Mowing Bad NASECA Feb 2014 1016-00-61

  12. Forestry Mowing Bad NASECA Feb 2014 1016-00-61

  13. Forestry Mowing Bad NASECA Feb 2014 1016-00-61

  14. Forestry MowingSummary • All work can be completed in one operation • Ability to complete work in frozen or snow covered conditions • Faster and more economical than traditional operations • Less ground disturbance (no grubbing, burying, or burning) • Less impacts to traffic (no debris to haul, minimal mobilization) • Few if any utility conflicts • Natural vegetation re-growth • Seeding and mulching not always needed

  15. Curlex Bloc • Curlex Blocs are a good alternative to Coir Logs. • USA made. • Made from naturally grown materials. • Materials are loosely packed, so vegetation can naturally root. • Great wicking material. NASECA Feb 2014 1390-04-79

  16. Curlex Bloc NASECA Feb 2014 1390-04-79

  17. Curlex Bloc NASECA Feb 2014 1390-04-79

  18. Curlex Bloc NASECA Feb 2014 1390-04-79

  19. Curlex Bloc NASECA Feb 2014 1390-04-79

  20. Curlex Bloc NASECA Feb 2014 1390-04-79

  21. Curlex Bloc NASECA Feb 2014 1390-04-79

  22. Curlex Bloc 3 months NASECA Feb 2014 1390-04-79

  23. Curlex Bloc NASECA Feb 2014 1390-04-79

  24. Curlex Bloc 6 months NASECA Feb 2014 1390-04-79

  25. Curlex Bloc NASECA Feb 2014 1390-04-79

  26. Curlex Bloc 16 months NASECA Feb 2014 1390-04-79

  27. Curlex Bloc NASECA Feb 2014 1390-04-79

  28. Curlex Bloc • Great Natural filter. • Good vegetative growth. • Biodegrades naturally. • Installation is the biggest problem • Imbed the Bloc, so it intercepts water. • Abut Blocs and overlap material to make a seamless joint. NASECA Feb 2014 1390-04-79