20 likes | 152 Views
Wind Operations Task Force. Status as of May 29, 2008 Previously closed issues #PDCWG1 & #PDCWG2 Recommending ROS endorsement of issue #3f Set target dates for issues # 1a, 1b, 1c, 1d, 2a, and 4. Issue 3f: “Run multiple CSC limit studies”. Recommending ROS endorsement:
E N D
Wind Operations Task Force Status as of May 29, 2008 Previously closed issues #PDCWG1 & #PDCWG2 Recommending ROS endorsement of issue #3f Set target dates for issues # 1a, 1b, 1c, 1d, 2a, and 4
Issue 3f: “Run multiple CSC limit studies” • Recommending ROS endorsement: • ERCOT to increase the frequency of calculating CSC limits to hourly, no Protocol change necessary • Three out of five CSCs completed (NtoS, StoN, NtoH), two to go