1 / 4

The restart of the NA after LS1

The restart of the NA after LS1. The proposal is made to Complete the irradiated cable replacement campaign in the LSS1 of the SPS in time for the start up of the cold checkout for June 27 th 2014

zuzana
Download Presentation

The restart of the NA after LS1

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The restart of the NA after LS1 • The proposal is made to • Complete the irradiated cable replacement campaign in the LSS1 of the SPS in time for the start up of the cold checkout for June 27th 2014 • Prepare the irradiated cable replacement campaign in the TDC2 of the North Area for October 13th until the start up of the commissioning with beam of the SPS • Carry-out a proton run of the NA between October 13th 2014 and December 15th 2014 • Complete the irradiated cable replacement campaign in the TDC2 of the North Area until April 15th 2015 (tbc) LS1 & the restart of the North Experimental Area

  2. the draft schedule 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 2014 2015 irradiated cable replacement campaign in the LSS1 Oct 13 Dec 15 Apr 15 SPS cold checkout Beam to NA Beam to NA Jun 27 irradiated cable replacement campaign in TDC2 (positioning) irradiated cable replacement campaign in TDC2 (completion) • Where the ion run for NA61 is scheduled in 2015 is still under study – could occur in January, before the NA shutdown. • The TCC2 cable replacement campaign is delayed to LS2 LS1 & the restart of the North Experimental Area

  3. An ion run in 2015 • If we want an ion run (NA61) in parallel with LHC commissioning early 2015, an additional interlock system requiring cables between BA5 and BA3 as well as BA2 and BA3 must be made available LS1 & the restart of the North Experimental Area

  4. The splitter area of the NA TDC 2 • Replacement, removal and relocation of cables transiting over the beam line two splitters LS1 & the restart of the North Experimental Area

More Related