Approach. . Gather Existing InformationReview Parish Survey CommentsExisting Building EvaluationDevelop Concept OptionsPreliminary BudgetDevelop DesignCost EstimatingFund DriveContract DocumentsConstruction Phase. Design Concept. . Keep warmth of existing space while providing a feeling of a Sacred space.Final design to respond to parish wide input.
E N D
1. Holy Spirit Renovation Project BACKGROUND
Start-up June 2005
Formed Committee
Church Visitations
Parishioner Input
Parish Forms November 2005
Parish Survey
Survey Results February 2006
Positive Response
Hired Architect March 2006
Completed Preliminary Design July 2006
3. Design Concept Keep warmth of existing space while providing a feeling of a Sacred space.
Final design to respond to parish wide input
4. Design Concept Responds to parish goals
Permanent Crucifix
New baptismal font near altar
Cry room relocated near toilets
New devotional areas added
New sanctuary furnishings and finishes
New gathering space allows space for tables, sign ups etc. without interfering with circulation
5. Conceptual Plan
6. Interior Elevations
7. Exterior Elevation