LCLS Injector-Linac Management Jose Chan

LCLS Injector-Linac Management Jose Chan. Injector/Linac Management. Organization Safety - Design and Installation Estimate to Complete Performance Installation Goals 2007 and 2008 Work Summary. LCLS Injector/Linac Organizational Chart. LCLS Injector/Linac Organizational Chart.

Download Presentation

LCLS Injector-Linac Management Jose Chan

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LCLS Injector-Linac Management Jose Chan

  2. Injector/Linac Management • Organization • Safety - Design and Installation • Estimate to Complete • Performance • Installation Goals • 2007 and 2008 Work • Summary

  3. LCLS Injector/Linac Organizational Chart

  4. LCLS Injector/Linac Organizational Chart • Mechanical engineers matrix into Injector/Linac organization • Installations are supported by different operation groups and/or contractors • Jim Turner coordinates all safety concerns with Safety Overview committees and has safety oversight for Linac • Continue to support commissioning

  5. Injector-Linac Integrated Safety Management • Define Scope of Work • Design of beamlines, systems and components • Laboratory downtime installation schedule • Analyze Hazards • Design Reviews: RF, lasers, electrical, Installation • Ray trace, Beam loss scenarios • Citizen committee reviews (SOC) • Develop/Implement Hazard Controls • PPS, laser safety, personnel training • Magnet terminal covers, lifting lugs, barriers, labeling • Installation Readiness Review • Fabricate Components, Install Beamlines • Safety tailgate meetings • Inspections – all hardware are signed off by physicist, engineer, control and metrology • Review safety performance • Integrate lessons learned into next cycle

  6. Injector • Injector completed installation in March 2007 • Closed all injector accounts • Commissioning started in April • Commissioning has been slow due to faulty hardware • Problems with quality of fabrication and installation of diagnostics • 2007 and 2008 installation hardware: we have instituted an RFI sign-off sheet, requiring approvals from physicist, engineering, controls and metrology

  7. Injector Cost and Schedule Variance • Schedule Variance Drivers: • All efforts were dedicated to Linac housing installation, thus delayed injector vault installation • Cost Variance Drivers: RF, Integration • RF Gun, Structures and Diagnostics, more effort required than estimated • Integration more complicated, unforeseen or inherited tasks

  8. LCLS Injector TEC SPA

  9. Linac Estimate to Complete • 2007 installation on schedule • September thru November 2007 • Installation of BC2 and L3, not L2 (in Linac housing) • Cable installation through the BSY • All parts in fabrication or are ready for installation • Implemented new material planning • Held Installation Readiness Reviews and PMOG 2007 installation review • 2008 installation planning is underway • Early Occupancy installation held constant at Nov. 1, 2007 • Installation of LTU and E-Dump – complete by October 2008 • All magnets are available for installation or have been ordered, except BYD which is out for quote • Completed design on standard drift length chambers • Installation drawings are almost complete • Support stands have been ordered (scheduled deliveries in September 2007) • Ready to place order for support stand installation in next two weeks • Integrated installation scheduling coordinated by R.M. Boyce

  10. LCLS Linac Level 3 Milestones • May 2007 data • Will meet scheduled milestones except - • LTU and E-Dump component installations • Wait for LTU Commissioning Start

  11. Linac Cost and Schedule Variance • Schedule Variance Drivers: Installation • L1 Install behind schedule, late components, deferred some installation • Designs for 2007 and 2008 delayed due to 2006 installation delays • Cost Variance Drivers: • Profile monitors; more types required than estimated • Under estimate cost of engineering, designs and fabrication • CR effects – uncertainties of LTU installation schedule

  12. LCLS LINAC TEC SPA

  13. Injector and Linac Installation Linac Down: September – November 2007 RF Gun installed Linac-X installed Inj Vault installed E-Dump Nov 2007 Oct 2008 L0-a,b Linac-3 Sep-Nov 2007 Linac-2 de-scoped Wire Scanners Linac-1 installed 25-1a 30-8c 21-3b 24-6d ...existing linac 21-1 b,c,d X DL-1 installed BC-1 installed BC-2 Sep-Nov 2007 LTU Nov 2007 Oct 2008 SAB installed SLAC linac tunnel research yard Installation in SLAC Linac tunnel only during down-times

  14. LCLS Installation and Commissioning Time-Line LTU/Dump Install First Spont. Light CF Early Occupancy e- beam & Photon Systems Checkout CD-4a S O N D J F M A M J J A S O N D J F M A M J J A S O N D 2007 2008 2009 PPS PPS Photon Flux Measurements Controls checkout Re-commission Inj/BC2 to SL2 LTU/Und/FEE Commissioning Linac/BC2 Commissioning BC2 & L3 Install FEL Commissioning

  15. 2007 and 2008 Linac Work Status • L2 Design –Done • BC2 Design – Done • L3 Design – Done • LTU Design –65% complete • E-Dump Design – 80% complete • CF Interface required for LTU & E-Dump • Jim Turner managing interface issues • Rad-Physics interface for LTU & E-Dump • J Langton shielding for E-Dump integrated system • T. Montagne shielding for LTU integrated system • Undulator interface • T. Montagne and J Langton

  16. Six Month Look Ahead • Complete BC2 and L3 installation & start commissioning • Perform system PDRs & FDRs for 2008 Installs • Pursue Safety Overview Committee (SOC) signoff for 2008 installations • Place BYD magnet order • Place diagnostic component orders for designed components • Finalize LTU & E-Dump vac system design and order components • Finalize shielding requirements LTU & E-Dump integrated systems • Finalize and close CF interface issues

  17. Injector/Linac Management Summary • Safety incorporated into design & installation • CF & Rad Physics interface ongoing • Continue to support commissioning • Manage cost and schedules to complete 2007 and 2008 installations • Plan to transition design staff into commissioning phase