1 / 40

Cost Allocation Studies for the MP Region

Cost Allocation Studies for the MP Region. Central Valley Project Cost Allocation Study Update Public Meeting March 16, 2012. Bureau of Reclamation April 29, 2008. Central Valley Project Cost Allocation Study. CVP-CAS. Meeting Purpose Continued Flood Control Discussions

Patman
Download Presentation

Cost Allocation Studies for the MP Region

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Cost Allocation Studies for the MP Region Central Valley Project Cost Allocation Study Update Public Meeting March 16, 2012 Bureau of Reclamation April 29, 2008

  2. Central Valley Project Cost Allocation Study CVP-CAS Meeting Purpose • Continued Flood Control Discussions • Hydrology Modeling Assumptions • Cost Estimating Methodology

  3. Central Valley Project Cost Allocation Study CVP-CAS Background • Last Meeting on 10/21/11 • Introduced Flood Control Purpose for Shasta • Hydrology Modeling Initial Assumptions • Estimating Single Purpose Alternative Costs • Flood Control Benefits (Corps)

  4. Central Valley Project Cost Allocation Study CVP-CAS Summary of Feedback Received • Public Involvement -More Frequent and Timely Meetings • CVP Facilities - Inclusions and Exclusions • Methodology • Support Efficiencies in Process • Hydrology Modeling - Assumption Questions • Estimating Costs - Concerns with Indexing vs. Re-pricing

  5. Central Valley Project Cost Allocation Study CVP-CAS Hydrology Analysis for Single Purpose Flood Control Operations Nancy Parker BOR Technical Services Center

  6. Hydrology Analysis for Single Purpose Flood Control Reservoir Sizing CVP-CAS - Hydrology Analysis • How much of the reservoir is used for flood control? • How big would a reservoir need to be to solely provide flood control? • This is not a probable maximum flood analysis • Analysis Methods • Flood Control Rule Curve • Daily Hydrology Model • Comparison to Historical Operations • Unique considerations for each facility

  7. Flood Control Rule Method CVP-CAS - Hydrology Analysis

  8. Flood Control Rule Method CVP-CAS - Hydrology Analysis

  9. Daily Hydrology Method CVP-CAS - Hydrology Analysis • Inputs - Minimum storage, inflow, evaporation rate, discharge rating curve, bathymetry, release criteria • Hydrology • Historical calculated daily inflow provided by CVO • Historical daily flows at downstream control locations • Acquired from CDEC • Used to calculate downstream accretions • Assumptions/Limitations • Accretions are not unimpaired • No reservoir routing • Monthly evaporation rates • Minimum Storage and Discharge Capacity • Assume levels used in current operations

  10. Daily Hydrology Method CVP-CAS - Hydrology Analysis

  11. Shasta Flood Control Facility CVP-CAS - Hydrology Analysis • Daily Model Assumptions/Controls • 79,000 cubic feet per second (cfs) maximum flow at Keswick • 100,000 cfs maximum flow at Bend Bridge • Historical accretions = Bend Bridge – Keswick • Minimum storage of 550 thousand acre feet (taf) • Operational Responsibilities • Flow standards at Red Bluff Diversion Dam • Flow standards at Wilkins Slough • Flow standards at Rio Vista • Delta Water Quality • Delta Outflow • Deliveries to Sacramento River CVP water users • CVP Delta Exports

  12. Shasta Rule Curve Method CVP-CAS - Hydrology Analysis • Examine monthly time series of Flood Control (FC) Rules • Max Capacity – Min FC Rule + Min Storage = Required Space

  13. CVP-CAS - Hydrology Analysis

  14. CVP-CAS - Hydrology Analysis Historical releases anticipate inflow event. Enabled by higher capacity for release at higher storage level.

  15. Shasta Summary(All Values in TAF) CVP-CAS - Hydrology Analysis

  16. Folsom Flood Control Facility CVP-CAS - Hydrology Analysis • Daily Model Assumptions/Controls • 115,000 cfs maximum release from Nimbus • Minimum storage of 90 taf • Operational Responsibilities • Flow standard below Nimbus • Flow standard at American River at H Street • Delta water quality • Delta outflow • Deliveries to American River contractors • CVP Delta Exports

  17. Folsom Summary (All Values in TAF) CVP-CAS - Hydrology Analysis

  18. New Melones Flood Control Facility CVP-CAS - Hydrology Analysis • Daily Model Assumptions • 8000 cfs maximum flow at Ripon • Historical accretions = Ripon – Goodwin • Minimum storage of 80 taf • Operational Responsibilities • Flow standard at Goodwin • Flow standard at Ripon • Dissolved Oxygen standard at Ripon • Water Quality standard at Vernalis • Flow standard at Vernalis • Deliveries to CVP Stanislaus River CVP contractors

  19. New Melones Summary(All Values in TAF) CVP-CAS - Hydrology Analysis

  20. Friant Flood Control Facility CVP-CAS - Hydrology Analysis • Daily Model Assumptions • Maximum release 8000 cfs • Maximum release 9000 cfs • Maximum storage 524 taf • Operational Responsibilities • San Joaquin River Restoration Flow Releases • Release for upper San Joaquin River water rights • Delivery to Friant Kern and Madera Canals • Unique Analysis Challenges • Direct delivery from reservoir to canals • Evolving consideration of flood flows in San Joaquin • Restoration reoperations modifying flood rules

  21. Friant Summary (All Values in TAF) CVP-CAS - Hydrology Analysis

  22. CVP-CAS – Cost Estimating Estimating Costs for Single Purpose Flood Control at Shasta Alan Stroppini Reclamation Design and Construction Division

  23. CVP-CAS – Cost Estimating Cost Estimating Goals • Easy to Apply • Easy to Understand • Scalable • Comparable to Other Cost Estimates • Comparable to Benefits Analysis

  24. CVP-CAS – Cost Estimating Cost Estimating Methods • Cost Indexing • Reclamation Indexes • Engineering News Record (ENR) Indexes • Building Cost Indexes (BCI) • Construction Cost Indexes (CCI) • Re-pricing Model

  25. CVP-CAS – Cost Estimating Cost Indexing – Reclamation Methods • Indexes Available 1940 to present • Published Quarterly by Reclamation • Developed to represent cost escalation associated with typical Reclamation facilities

  26. CVP-CAS – Cost Estimating Cost Indexing – ENR CCI Method • Indexes Available 1908 to present • Published Quarterly by ENR • Developed based on the following • 200 hours of common labor at the 20-city average of common labor rates • 25 cwt of standard structural steel shapes at the mill price prior to 1996 and the fabricated 20-city price from 1996 • 1.128 tons of portland cement at the 20-city price • 1,088 board-ft of 2 x 4 lumber at the 20-city price

  27. CVP-CAS – Cost Estimating Cost Indexing – ENR BCI Method • Indexes Available 1915 to present • Published Quarterly by ENR • Developed based on the following • 68.38 hours of skilled labor at the 20-city average of bricklayers, carpenters and structural ironworkers rates • 25 cwt of standard structural steel shapes at the mill price prior to 1996 and the fabricated 20-city price from 1996 • 1.128 tons of portland cement at the 20-city price • 1,088 board-ft of 2 x 4 lumber at the 20-city price

  28. CVP-CAS – Cost Estimating Cost Index Comparison for Concrete Dams

  29. CVP-CAS – Cost Estimating Shasta Multi-Purpose FacilityIndexing Results – 4.5 MAF

  30. CVP-CAS – Cost Estimating Re-pricing Model • Based on Bid Abstract Analysis • Define Major Bid Items in Abstract • Develop Unit Prices for Identified Major Items • Consider Other Cost Items, including • Mobilization • Design & Construction Contingencies • Other Non-Contract Costs • Develop Project Cost Model Comparable to Plant-in-Service Cost Representation

  31. CVP-CAS – Cost Estimating Shasta Dam and Powerplant Abstract Analysis

  32. CVP-CAS – Cost Estimating Develop Unit Prices for Major Bid Items Add-On Percentages

  33. CVP-CAS – Cost Estimating Shasta Dam & Powerplant: Contract/Field Costs Re-Priced Bid Item Quantity Cost Final Cost _________________________________________________________________________________________________________________________ Concrete 6,300,000 $ 200 $ 1,260,000,000 Excavation 4,000,000 $ 24 $ 96,000,000 Rebar 31,000,000 $ 2 $ 62,000,000 Rockfill/Emb 1,800,000 $ 10 $ 18,000,000 _________________________________________________________________________________________________________________________ Mobilization (5%) $ 72,000,000 Design Contingency (15% +/-) $ 122,000,000 _________________________________________________________________________________________________________________________ Contract Cost $ 1,730,000,000 Construction Contingency (5% +/-) $ 90,000,000 _________________________________________________________________________________________________________________________ Field Cost $ 1,820,000,000

  34. CVP-CAS – Cost Estimating Project Cost Estimating Model

  35. CVP-CAS – Cost Estimating Shasta Dam and Reservoir Cost Curve Development

  36. CVP-CAS – Cost Estimating Multi-Purpose Shasta Size: 4.5 MAF Re-priced Cost: $5.0 Billion +/- Shasta Flood Control Size: 2.0 MAF Re-priced Cost: $3.0 Billion +/-

  37. Analysis Summary CVP-CAS

  38. Next Steps CVP-CAS • Review and Respond to Comments Received • Refinement of Process and Schedule • Upcoming Public Meetings • June 29, 2012 • September 21, 2012 • December 14, 2012

  39. Next Steps: Process & Schedule CVP-CAS 2010-2011 2012-2013 • Flood Control • Navigation • Recreation • Power • Water Supply • Water Supply (cont.) • Water Quality • Fish & Wildlife 2014-2015 • Draft Allocation • Prepare Report 2016 Ongoing Public Involvement • Methodology • Assumptions • Work Plan

  40. www.usbr.gov/mp/cvp/cvp-cas/index.html CVP-CAS Traci Michel, Project Manager tmichel@usbr.gov

More Related