Minuteman Vocational Technical Regional High School Progress

Minuteman Vocational Technical Regional High School Progress. June 17 th 2019 – July 15 th 2019. July 15 th View of Area A+B – Upper Level Classrooms floor protection has been removed. Washing & waxing completed for furniture. July 15 th View of Area A+B – Lower Level

adean
Download Presentation

Minuteman Vocational Technical Regional High School Progress

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Minuteman Vocational Technical Regional High School Progress June 17th 2019 – July 15th 2019

  2. July 15thView of Area A+B – Upper Level Classrooms floor protection has been removed. Washing & waxing completed for furniture. July 15thView of Area A+B – Lower Level Electrical Lab space has been cleaned and concrete floors sealed.

  3. July 15thView of Area D – Upper Level Typical classroom on floor, floor protection has been removed. Washing & waxing completed for furniture. July 15thView of Area D – Lower Level Ceiling grid and MEP devices complete. Epoxy flooring system complete.

  4. July 15thView of Area D – Gymnasium Bleacher construction in progress. Wall pad installation to follow.

  5. July 15thView of Area E – Upper Level Media center carpet complete. Millwork desk substantially complete. July 15thView of Area E – Lower Level Main entrance corridor. Ceramic floor tile setting & grouting in progress.

  6. July 15thView of Area E+F – Cafeteria Ceramic wall tile complete. Vinyl floor tile complete & protected. Furniture staging area

  7. July 15thView of Area F – Lower Level Millwork installation substantially complete Plumbing fixtures installation complete. Vinyl floor tile installed & protected. Final connections of Kitchen Equipment in progress in both kitchens.

  8. July 15thView of Area C – Theater-Audience Side Lighting, electrical power and audio visual rough-in complete at the Tension Grid. July 15thView of Area C – Theater-Stage Side Installation of counter weight rigging complete, stage right. Rigging cables being run for connection of battens.

  9. July 15thView of Area E – Courtyard Landscape pavers complete. Plantings substantially complete. Pre-cast wall cap installation in progress.

  10. July 15thView of Area E – Main Entrance Landscape pavers & granite bollards complete.

  11. July 15thView of Faculty Parking Lot Landscape pavers in progress at faculty lot. Prepping & Placing on concrete speed tables in progress.

  12. July 15thView of Student Parking Lot Subgrade prep substantially complete. Rain garden drainage assemblies excavated & prepared for system.

  13. July Construction Schedule Look Ahead: Area A+B & G • Complete Concrete Sealant of Shop Floors • Continue Punchlist Process • Commence Signage Installation Area D • Complete Wall Pad, Bleachers and Scoreboard installation • Complete plumbing fixture & toilet partition installation in Locker Rooms • Continue Punchlist process • Commence Signage Installation Area E • Complete Corridor flooring Installation on Upper & Lower Level • Complete ceramic floor tile installation at Main Entrance corridor • Continue Carpet tile installation in remaining rooms. Area F • Complete with installation of Millwork • Complete installation & connections of Kitchen equipment • Commence restaurant patio framing & decking Area C • Complete Counterweight & Guidewall Rigging Installation • Commence millwork panel installation • Commence stage flooring installation Exterior/Sitework • Complete installation of granite curbing in faculty parking lot • Complete with placing concrete sidewalks and speed tables • Complete the installation of landscape pavers in faculty parking lot • Continue with landscaping plantings at perimeter of site • Continue with fill & utility installation in the Student parking lot • Next paving activity scheduled for the Week of 7/22

  14. Project Turn-Over Schedule Look Ahead: