450 likes | 703 Views
2. Integrated Schedule Review. December 10, 2008. Agenda. Program Changes (Janet Ply)Preliminary Nodal Integrated Master Schedule (Janet Ply)Scope (Janet Ply)Schedule Assumptions (Janet Ply)Work Remaining by Project (Core PMs)Integration Activities (Mike Bianco)EDS Activities (Matt Mereness)K
E N D
1. December 10, 2008 TPTF Integrated Schedule Review Nodal PMO
2. 2 Integrated Schedule Review December 10, 2008 Agenda
3. 3 Integrated Schedule Review December 10, 2008 Program Changes Reorganized the entire program to eliminate project silos; instill accountability; put the right people in the right roles; streamlined delivery
Changed leadership: Ron Hinsley is the Executive Sponsor and the Executive Director; Janet Ply now leads the nodal Program Management Office (PMO)
Projects were reorganized into core and supporting projects; core projects own end-to-end delivery
Developed a Nodal Master Integrated Schedule; identified hundreds of project inter-dependencies that were previously unknown
Developed comprehensive program controls that are used rigorously to manage work
Increased executive involvement in anything that affects program scope
Increased vendor oversight and vendor accountability; have put ERCOT staff onsite and have vendor staff onsite at ERCOT during critical times
Staffing has been reviewed; 108 contractors have left the nodal program since June; 18 contractors have been converted to ERCOT employees
Increased ERCOT home team involvement in several key areas Resource Asset Registration Form (RARF)Resource Asset Registration Form (RARF)
4. 4 Integrated Schedule Review December 10, 2008 Restructured Projects Network Model Management System
Linda Clarke leads this effort
Established data quality teams for the RARF data collection from Market Participants and for “nodalizing” the zonal seed for the network model (Common Information Model (CIM))
ERCOT Readiness and Transition
Murray Nixon leads ERCOT readiness and transition (i.e. business process development)
EDS
Matt Mereness leads EDS and MP readiness metrics
Enterprise Integration Services, Integration Testing
Combined these projects, renamed to Systems Integration and moved under the PMO
Mike Bianco leads this effort and comes from CAISO
Consolidated the zonal and nodal integration testing teams into one, added structure
COMS team
Hope Parrish, ERCOT Manager, leads this team
Justin Rasberry brought in to oversee Settlements and Billing and Commercial Systems Interfaces (CSI)
Reorganized the Credit Management and Monitoring (CMM) team to accelerate progress Resource Asset Registration Form (RARF)Resource Asset Registration Form (RARF)
5. 5 Integrated Schedule Review December 10, 2008 Results of Changes A high level of executive oversight and involvement
The right people in nodal leadership positions
Strong program controls and processes
Vendor focus
Team member accountability
Sense of urgency to deliver the Nodal program on schedule
6. 6 Integrated Schedule Review December 10, 2008 Preliminary Nodal Integrated Master Schedule In June, PMs replanned the nodal program across all project teams resulting in
An improved understanding of the scope of the work required through go-live, now scheduled for Dec.1, 2010
A comprehensive understanding of cross project dependencies for the nodal program
A detailed integrated master schedule for the nodal program that is the single source of record for all nodal work to be performed (~5400 activities)
Most importantly, a realistic schedule with a high degree of confidence that the nodal program can be delivered on schedule
Integrated master schedule has undergone numerous reviews and audits
ERCOT has been using this integrated schedule and supporting reports successfully to manage the program and project critical paths
ERCOT needs to incorporate MP activities and feedback, scheduled for TPTF meeting on Tuesday, Dec. 16, before the schedule can be finalized
7. 7 Integrated Schedule Review December 10, 2008 Scope Nodal program scope included in the integrated schedule
Approved requirements and conceptual system design documents
All NPRRs approved through Nov.17, 2008
Additional scope to process to be included
Remaining business process work
Remaining requirements traceability work
No impact to the program critical path for this work
Note 1: No schedule contingency has been included in the integrated master schedule; any additional scope/effort that is required will go through the nodal change control process and impacts to the schedule and budget will be captured
Note 2: Removing and/or clarifying scope that affects any of the nodal systems at this point does not necessarily decrease effort
8. 8 Integrated Schedule Review December 10, 2008
9. 9 Integrated Schedule Review December 10, 2008 Schedule Assumptions No new software vendor releases will be required past what is already planned (remaining scheduled releases will be covered in each individual project)
Preserved the EDS durations as defined in the handbooks
Market participant activities that were placed on hold are not restarted until the NMMS/EMS/MMS5 systems are on a synchronized model (schema and data set)
Market participants will continue to participate in ongoing nodal EDS activities
10. 10 Integrated Schedule Review December 10, 2008 Work Remaining – NMMS
11. 11 Integrated Schedule Review December 10, 2008 Work Remaining - Model Dec.10: Synchronized Model (v1.21 schema and data set)
Jan. 8: Validated Model (v1.21 schema and data set)
Mar. 9: Validated Model with Final RARF data (v1.21 schema and data set)
12. 12 Integrated Schedule Review December 10, 2008 Work Remaining – EMS
13. 13 Integrated Schedule Review December 10, 2008 Work Remaining – MMS
14. 14 Integrated Schedule Review December 10, 2008 Work Remaining – MMS UI
15. 15 Integrated Schedule Review December 10, 2008 Work Remaining – Outage Scheduler
16. 16 Integrated Schedule Review December 10, 2008 Work Remaining – CRR
17. 17 Integrated Schedule Review December 10, 2008 Work Remaining – COMS
18. 18 Integrated Schedule Review December 10, 2008
19. 19 Integrated Schedule Review December 10, 2008 Outline of Discussion Breadth of Integration Work
What’s Remaining?
Integrated Releases
Integrated Release 4 Activities
Integrated Release 5 Activities
Operational Readiness Activities
20. 20 Integrated Schedule Review December 10, 2008 Breadth of the Systems Integration Effort
21. 21 Integrated Schedule Review December 10, 2008 Integrated Release Milestones
22. 22 Integrated Schedule Review December 10, 2008 Integrated Release Timeline
23. 23 Integrated Schedule Review December 10, 2008 Integrated Release 4 Activities
24. 24 Integrated Schedule Review December 10, 2008 Integrated Release 5 Activities
25. 25 Integrated Schedule Review December 10, 2008 Operational Readiness Activities
26. 26 Integrated Schedule Review December 10, 2008
27. 27 Integrated Schedule Review December 10, 2008 Outline of Discussion Revisit why EDS4 DAM/RUC/Settlements testing stopped
Lessons Learned from EDS in 2007/2008
Current EDS Delivery Challenges
Details of 2009 Market Activities
Monthly view of 2010 Market Activities
28. 28 Integrated Schedule Review December 10, 2008 Revisit why EDS4 DAM/RUC/Settlements testing stopped Behind schedule in delivering a validated model with final RARF data
Significant workarounds put in place but did not solve the integrity problems
DAM results were not meaningful due to data issues
MP involvement declined over time when DAM results were not valid
ERCOT system integration components were not in place
29. 29 Integrated Schedule Review December 10, 2008 Lessons Learned from EDS in 2007/2008 ERCOT Benefits
Visibility of market generated bids/offers and submission structures
More production-like testing of Web Services & Market rules
Earlier feedback from Market Participants
Market Benefits
Exercised interfaces with ERCOT
Better understanding of how the technology and rules are implemented
Opportunity for end-users to put hands on the systems
Opportunity to receive and analyze data from ERCOT to load into MP systems
ERCOT Challenges
MP integration was prioritized over internal integration
Throw-away development of work-arounds to overcome system limitations
Project SMEs were pulled to support EDS issues
30. 30 Integrated Schedule Review December 10, 2008 EDS and Market Activities 2009
31. 31 Integrated Schedule Review December 10, 2008 EDS and Market Activities 2009
32. 32 Integrated Schedule Review December 10, 2008 EDS 2010 Timeline
33. 33 Integrated Schedule Review December 10, 2008 Feb 2010 – Resume EDS on integrated systems EDS activities
Execute SCED with the objective of publishing LMPs for 6 months
Publish SCED reports (RT LMPs etc)
Test communication of DAM inputs and outputs
Execute DAM 2 days per week with Market Data
Post AS Obligation, QSE Load Ratio Share, AS plan
Issue DAM Awards and Notifications (Awarded AS, Awarded Energy bid etc)
Publish DAM hourly reports (DAM LMPs, DAM MCPC etc)
Conduct mock CRR annual auction
Publish CRR auction results
Outage Scheduler open to MPs for submissions
Perform Outage Evaluation testing
Publish Outage Scheduler reports (Approved outages, rejected etc)
Publish Available Credit Limit on MIS
Seek TPTF approval for test Network Model to be used for Settlements testing
34. 34 Integrated Schedule Review December 10, 2008 Mar 2010 – Execute DAM and RUC, publish Settlements for DAM and conduct CRR auction EDS activities
Continue execution of SCED for publishing LMPs for 6 months and publish reports
Continue execution of DAM 2 days per week with Market Data, issue notifications and publish results
Conduct 2 hour LFC test with CIM
Execute HRUC and DRUC 2 days per week with Market Data
Publish RUC results
Committed and decommitted units
Active binding transmission constraints used in RUC
Publish Settlement Statements, Invoices and Extracts for DAM
DAM Settlement and Resettlement Statement
CRR Balancing Account Invoices
DAM Invoice
CARD Invoices
DAM Resettlement Invoice
DAM Late Fee Invoices
DAM Consolidated Operating Day Extracts
DAM Market Operating Day Extracts
Public Reference Data Extract
Settlement Input Data Extract
Conduct OS Performance test
Publish test CRR annual auction results
Conduct Integrated CRR monthly auction
35. 35 Integrated Schedule Review December 10, 2008 April 2010 – Execute DAM 5 days per week, publish RTM Settlement statements and conduct LFC tests EDS activities
Continue execution of SCED for publishing LMPs for 6 months and publish reports
Publish mock Integrated CRR auction results
Conduct 8 hour LFC test with CIM
Execute DAM and DRUC 5 days per week, issue notifications and publish results
Execute HRUC 4 days per week
Begin SASM execution
Issue SASM notifications
Awarded AS offers
Publish SASM reports
SASM MCPC
Total Ancillary Service procured
Aggregated Ancillary Service Offer
Publish Settlement Statements, Invoices and Extracts for RTM and DAM
RTM Initial, Final, True-up and Resettlement Statement
RTM Initial, Final, True-up and Resettlement Invoice
RTM Consolidated Operating Day Extract (RTM CODE)
RTM Market Operating Day Extract (RTM MODE)
Public Reference Data Extract (PRDE)
Settlement Input Data Extract
Begin testing of Disputes submission process through UI and API
36. 36 Integrated Schedule Review December 10, 2008 May 2010 – Test full market timeline for 7 days and settle market EDS activities
Continue execution of SCED for publishing LMPs for 6 months and publish reports
LFC test analysis and reporting of results to Market Participants
Continue execution of DAM and DRUC 5 days per week, issue notifications and publish results
Continue execution of HRUC 4 days per week
Continue SASM execution
Continue publishing of DAM and RTM Settlement Statements, Invoices and extracts
Execute full Market timeline for 7 seven days
Produce Settlement statements for the full market timeline
One day dual entry of Outages into Zonal and Nodal systems
37. 37 Integrated Schedule Review December 10, 2008 June 2010 – Conduct 48 hour LFC test and conduct integrated CIM business process testing EDS activities
Publish RT and DAM settlements for Full market timeline
Execute 48 hour LFC test
Execute EECP test
Continue execution of SCED for publishing LMPs for 6 months and publish reports
Continue execution of DAM and DRUC 5 days per week
Continue execution of HRUC 4 days per week
Continue publishing of DAM and RTM Settlement Statements, Invoices and extracts
Conduct CIM business process testing
7*24 support of Nodal systems
Validate EDW Compliance Data Access
38. 38 Integrated Schedule Review December 10, 2008 July 2010 – Verify LMP quality and conduct DAM/RUC/SCED performance test EDS activities
Continue execution of SCED for publishing LMPs for 6 months and publish reports
Complete posting of LMPs for 6 months
Continue execution of DAM and DRUC 5 days per week
Continue execution of HRUC 4 days per week
Continue publishing of DAM and RTM Settlement Statements, Invoices and extracts
Execute DAM/RUC/SCED performance test
Conduct DST Test with Market Participants
Begin verification of MIS compliance with Requirements
Conduct fail-over test(s)
39. 39 Integrated Schedule Review December 10, 2008 August 2010 – 48 Hour full market timeline test and preparation for 168-Hour test EDS activities
Continue DAM/RUC/SCED performance tests
Execute DST test
Execute 48 hours of full market timeline without Sev 1 or Sev 2 errors
Complete verification of MIS compliance to Requirements
Complete execution of Fail-over tests
Complete verification of Dispute Process
7 day forecast validations/retraining
Conduct test monthly CRR auction for 168-Hour test
Align for 168-Hour Test
Qualification - QSE declaration of intent to participate in Nodal
40. 40 Integrated Schedule Review December 10, 2008 Sept 2010 – Completion of 168-Hour test and the Go-Live Period
41. 41 Integrated Schedule Review December 10, 2008 EDS & Cut-over Plans EDS 1 Approach: TPTF approved Feb 2008 as being completed - http://nodal.ercot.com/docs/pd/eds/eds1/eds1/eds_1_approach_v2_0.doc
EDS 2 Approach: TPTF Approved May 2007 -http://nodal.ercot.com/docs/pd/eds/eds2/eds2/EDS_2_Approach_v1_00.doc
EDS 3 approach: TPTF approved June 2007 - http://nodal.ercot.com/docs/pd/eds/eds3/eds3dp/EDS_3_Approach_v1.0_061107.doc
SCED Handbook v4: TPTF Approved Feb 2008 - http://nodal.ercot.com/docs/pd/eds/eds3/scedhdbk/eds_3_sced_mp_handbook_v4_0.doc
LFC Handbook v2: TPTF approved April 2008 -http://nodal.ercot.com/docs/pd/eds/eds3/lfchandbook/eds_3_lfc_testing_market_participant_handbook_v2_0.doc
CRR Handbook v2: TPTF approved Jan 2008 - http://nodal.ercot.com/docs/pd/eds/eds3/crrhandbook/eds_crr_testing_mp_handbook_v2_0.doc
EDS 4 Approach: TPTF approved Dec 2007 - http://nodal.ercot.com/docs/pd/eds/eds4/eds4app/eds_4_approach_v1_0.doc
COMS Handbook: TPTF Approved Feb 2008 - http://nodal.ercot.com/docs/pd/eds/eds4/eds4coms/eds_coms_mp_handbook_v1.0.doc
DAM/RUC Handbook v2: TPTF Approved March 2008 - http://nodal.ercot.com/docs/pd/eds/eds4/eds4damrucsasm/eds4_dam_ruc_sasm_mp_handbook_v2_0.doc
Outage Scheduler Handbook: TPTF Approved March 2008 - http://nodal.ercot.com/docs/pd/eds/eds4/eds4os/eds_outage_scheduler_mp_handbook_v1_0.doc
Day-light Savings Test Plan: TPTF Approved July 2008 - http://nodal.ercot.com/docs/pd/eds/eds4/dsttp/eds_dst_test_plan_v1_0.doc
EECP Test Plan: TPTF Approved May 2008 - http://nodal.ercot.com/docs/pd/eds/eds4/eotp/eds_emergency_operations_test_plan_v1_0.doc
168 Hr Test procedure: TAC Approved July 2008 http://nodal.ercot.com/docs/pd/eds/eds4/168htp/texas_nodal_market_168_hour_test_procedure_v1_0.doc
Single Entry Model Go-Live Procedure: TAC Approved Aug 2008 - http://nodal.ercot.com/docs/pd/eds/eds2/semglp/tnm_sem_go_live_procedure_v1_0.doc
Texas Nodal Market Go-Live Procedure: TAC Approved Jun 2008 - http://nodal.ercot.com/docs/pd/eds/eds4/glp/texas_nodal_market_go_live_procedure_v1_0.doc
TCR to CRR Transition Plan: TAC Approved Nov 2007 http://nodal.ercot.com/readiness/golive/kd/crr_tcr_to_crr_transition_plan_v1_0.doc
42. 42 Integrated Schedule Review December 10, 2008 Key Program Milestones through Go-Live View handouts:
Nodal Program Timeline 2009
Nodal Program Timeline 2010
43. 43 Integrated Schedule Review December 10, 2008 Critical Path Program critical path is the following
NMMS through Jan. 8, 2009 when the validated model (v1.21 schema and data set) is delivered for consumption by downstream systems (e.g. MMS, EMS, and CRR)
MMS5 is critical path from Jan. 9, 2009 – Aug. 24, 2009
Integrated Release 5 is critical path from Aug. 24, 2009 – Feb. 8, 2010
EDS is critical path from Feb. 9, 2010 – Dec. 1, 2010
View handout: Nodal Program Critical Path
44. 44 Integrated Schedule Review December 10, 2008
45. 45 Integrated Schedule Review December 10, 2008 Next Steps