Prince William Sound Regional Citizen’s Advisory Committee Board Meeting May 4, 2007. Health, Safety & Environment. 2007 VMT Major Focus Areas. Safety Process Safety Management LPS Trend analysis Integration of “Lessons Learned†90s Tank – Vapor Recovery System Tank 55 and Tank 56
E N D
Prince William SoundRegional Citizen’s Advisory CommitteeBoard MeetingMay 4, 2007
2007 VMT Major Focus Areas • Safety • Process Safety Management • LPS • Trend analysis • Integration of “Lessons Learned” • 90s Tank – Vapor Recovery System • Tank 55 and Tank 56 • East Tank Farm – Internal Tank Inspections • Allison Creek turbidity • 2007 Corrosion Action Plan
2007 VMT Projects • BWT Vapor Recovery • BWT Pilot Studies • Tank Program • Corrosion • Main Gate
Ballast Water Treatment Renovation Program • Completed the installation of the Biological Treatment Tank (BTT) recycle pump • Currently undergoing the Functional Check Out phase • Completed the final hookup to the Dissolved Air Floatation (DAF) BETX analyzer • Currently undergoing the Functional Check Out phase. • Initiated testing on the Phase Extraction Technology (PET) air stripper pilot unit - Testing is ongoing • Initiated testing on the PhotoCat pilot unit • The unit is offline awaiting resolution of reliability issues before further testing resumes • Advanced the work on the oil/water analyzer and new DAF and BTT sump re-route work - Project not yet completed • Continued working to install new Dissolved Oxygen and Salinity probes throughout the BWT processes - Project on-going • Completed the tank 80 headspace nitrogen inerting system
VMT Operational Status • BWT Tank 92 Spill • Temporary patch installed • Root Cause Analysis completed, and under review • Smoking incident • Safety Stand-downs conducted • Investigation conducted • Hydrotek steam cleaner incident • Investigation in process • Otter Hospital • Set up completed in 48 hours; C-Plan compliance requires 72 hours
VMT Operational Status Continued • Power/Vapor “B” Boiler • Corrosion discovered during scheduled inspection • Extent of condition under evaluation • The east potable water plant and VFF are fully operational • High turbidity from Allison Creek from the 2006 Flood impacted the operation • Berth 4 and Berth 5 quarterly maintenance was completed • Fierce Conversations training