An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BCTS Contracting Practices Summary of Audit Findings April 2007

  2. BCTS Contracting Practices • 7 Business Areas audited to date: • Seaward tlasta • Babine • Cariboo Chilcotin • Stuart Nechako • Prince George • Okanagan Columbia • Skeena • 4 more planned for 07/08

  3. BCTS Contracting Practices • Numerous examples of fine contract management have been observed. • Significant improvement in many of the contracting practices identified as deficient in previous audits and reviews

  4. Good Practices • Overall contract documentation • Advertising and award practices • Number of direct awards. • Invoice payment processes • Use of check lists and data sheets • Use of equipment hire • Management oversight of planning

  5. Areas for Improvement • Co-ordination of planning and activities • Management Oversight / Risk Management • Training • DAs & Equipment Hire • RFPs – OTR & Multiyear contracts

  6. Co-ordination of planning and activities • A lack of co-ordination of contracting activities within Business Area between field-teams is creating inefficient and less than effective contracting practices.

  7. Co-ordination of planning and activities • Increased risk of unfair, or perceived unfair, contracting practices • Not consistent with the BCTS business model • Not client service focused • Has resulted in contractor complaints

  8. Co-ordination of planning and activities • Contracting risks will be reduced and the effectiveness of contracting practices increased by ensuring that Business Areas function as a single business unit

  9. Management Oversight / Risk Management • Increased involvement and oversight by the TSM and BALT is required • Mgmt oversight in planning and monitoring to ensure appropriate accountability and level of risk. • Introduction of regular periodic management reporting

  10. Management Oversight / Risk Management • Ensure sound principles of risk management underscore contract decisions. • Too frequently high-risk contracting decisions are being made by Contract Coordinators.

  11. Management Oversight / Risk Management • The number, type, award method and value of contracts by contractor should be reviewed. • To ensure the achievement of the fundamental contracting objective for fair access to government business. • More holistic long-term planning within Business Areas to help ensure both contract and business risks are adequately addressed

  12. Management Oversight / Risk Management • The Business Officers not used effectively or as is intended. • Should assume a greater leadership role. • Ensure that effective contracting accountability and performance management frameworks are in place. • Provide assurance that contracting practices are effective and in compliance with ministry contracting policies.

  13. Training More training is required. • A lack of understanding of risk, contracting principles, law, and policies has led to inappropriate policy interpretation or avoidance resulting in: • Inappropriate practices and award decisions. • Lack of fair access to work. • The acceptance of individual and Business Area risks well above reasonable levels.

  14. DAs & Equipment Hire • Number of direct awards and use of equipment hire still an issue in some locations. • Other locations have significantly reduced the number of directly awarded contracts and equipment hire agreements.

  15. RFPs – OTR & MY Contracts • Inappropriate use of RFPs and OTR & MYC increase risk of not providing fair access to work. • RFPs for silviculture contracts not consistent with policy. • OTR & MYC changes to tender and contract terms not always consistent with policy.

  16. RFPs – OTR & MY Contracts • Fail to achieve objective for defensible and justifiable contract awards. • Have resulted in several complaints of unfair award practices. • Significant legal exposure.

  17. RFPs – OTR & MY Contracts • Contracting risks will be reduced by ceasing to use Requests for Proposals and increasing the use of Invitations to Tender to procure silviculture services.

  18. Sharing Lessons & Best Practices • Final Reports and Action Plans all on BCTS HQ Corporate Operations web site.

  19. BCTS Contracting Practices • Questions? • Comments?