1 / 23

ISIS TS1 Project: Shutdown & Commissioning planning

ISIS TS1 Project: Shutdown & Commissioning planning. Stephen Gallimore Project Manager for the ISIS TS1 Project. ICANS XXIII – Chattanooga, TN, USA 15 th October 2019. Contents. Introduction Planning & Strategy Pre-installation testing Shutdown Strip-out & installation

akira
Download Presentation

ISIS TS1 Project: Shutdown & Commissioning planning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ISIS TS1 Project:Shutdown & Commissioning planning Stephen Gallimore Project Manager for the ISIS TS1 Project ICANS XXIII – Chattanooga, TN, USA 15th October 2019

  2. Contents • Introduction • Planning & Strategy • Pre-installation testing • Shutdown • Strip-out & installation • Commissioning • Summary

  3. Introduction – Project Overview • 9 years • £15M • Sustainability project to secure the operational future of ISIS TS1 Close-up of the target, reflector and moderators (TRaM) CAD render of full target trolley showing TRaM & services trolley

  4. Planning & Strategy What do we need to do to be ready for beam? What do we need the beam to do?

  5. Planning & Strategy • Overall commissioning strategy document • High level aims • Description of lower level documents • Layout of phases with expecting timings • Work package commissioning plans • Equipment specific • What is being tested and why • Discussion of scheduling and resources • Specific testing plans • Testing procedure • Tolerances of acceptance • Non-conformity & defects • Sign-off

  6. Planning & Strategy

  7. Pre-installation testing • Site Acceptance Test • Dimensional checks • Sub-set of FATs • Functional operation and mechanical fit • Flow rates & pressure drops • Alignment & adjustability • Basic controls system operations • Sensors reading sensibly • Valve operation Replica reflector and 3D printed moderator heads on the new cantilever frameTS1

  8. Pre-installation testing • Regular (maintenance/removal) remote handling • Disconnection and reconnection of services • Putting in a flask • Taking a target in and out of a storage well • Recovery from off-normal scenarios • For example, recovery from a dropped TRaM component A view through the ZnBr remote handling cell window on TS1

  9. Pre-installation testing • Procedure practice • Reduce time and dose to workers • Clear thinking in emergencies • Feeds into safety documentation required • Important to have sensible hold points • Sign off equipment as ready • Note any non-conformities & rectifications • Feedback parameters into design calculations • Permission to strip-out existing redundant equipment • Have agreed criteria • Prerequisite to starting shutdown • …once strip-out begins there is no going back!

  10. The Long shutdown • 12 months off for TS1 but cycle(s) run on TS2 • Planned to begin Sep 2020 • Rough breakdown of timings: • 3 months strip-out • 3 months install • 3 months pre beam commissioning • 3 months with beam commissioning • First few cycles after start up, there will be disruption

  11. The Long shutdown Some of the challenges: • Resources • Remote handling operatives • Shared resources (numbers and dose) • Two parallel working fronts (RHC & TSA) • Work flow bottle-necks • Main hall crane • Waste acceptance processes • Shared resources (?)

  12. The Long shutdown Some of the challenges: • Working environment hazards • Trolley movement • Multi-height parallel working • Radiation dose • Ambient conditions • Other large projects during shutdown • Linac tank IV replacement • Riken refurbishment • Instrument projects (various)

  13. RHC based strip out A CAD image of the current TRaM design with the reflector cut-away to show internal components

  14. RHC based strip out • Most major items have been removed before • Only cantilever frame has never been out • Frame will be cut in half* • Have clear, controlled and well practised procedures from removal and extraction of equipment • Highest dose rate items but very limited chance for exposure • Each item will be put into a shielded storage container *For more information please see the poster: ISIS TS1 Project – Removal of the Target, Reflector and Moderator (TRaM) Support Structure using a Bandsaw within a Remote Handling Cell. By Ross Turnley – 17th Oct @ 16:30

  15. TSA based strip out A photo from the construction of the target services trolley (circa 1983) showing the vast array of services’ pipework

  16. TSA based strip out • A lot of equipment to remove • Plan to remove highest dose rate items first i.e. filters, IEx columns & water pumps • Have clear waste plan for how to deal with all the different types of waste/waste items • Much work will require RPE as well as PPE • Work to utilise hydraulic cropper for cutting wherever possible • Workers will be exposed to many hazards, so training and preparation are essential

  17. Installation • Much equipment design in modular fashion to aid installation • Greater attention paid to remote handling features • Have worked closely with the operators of the equipment in the design phase • Most equipment will have been assembled & tested prior to installation • For RHC installation, aim is to minimise amount of remote handling work required • More care required than for strip-out!

  18. Commissioning without beam • Checking of connections and fit into greater system • Full without beam process and control functions: • Flow water through TRaM components • Cool-down and flow cryogens for moderators • Perform drain/vent/maintenance procedures on systems • How to deal with non-conformity and deviations • Installation complete • Hold point - Sign off of equipment and systems • Mechanical • Controls • DSEAR/ATEX

  19. Commissioning with beam • Radiation protocol and monitoring • Staged commissioning with increasing power steps • Need to provide expected beam requirements to accelerator team • High enough power to get meaningful heat loads • Keep power as low as possible to minimise activation • Check parameters against designs • Will require some instruments to open shutters • Commissioning complete • Hold point – Hand over to operations

  20. Summary • Outline Commissioning plans in existence, detailed commissioning and resource plans to be developed • Schedule is tight: • Late delivery has an impact on pre-install testing • Delays during strip-out & install ‘squeeze’ commissioning • Resources constraints & bottle-necks • TSA strip out likely to lead to highest doses to workers • Must have robust and practiced procedures • Hand-in-hand relationship with safety documentation

  21. If you have any questions I would now be happy to take them Thank you for your Attention

  22. Back-up slides

  23. Pre-installation testing TRaM components: • Alignment • Where possible functional tests; i.e. water flow • Cutting saw final practice cuts Target services area components & systems: • Basic water flow & valve operation testing • Simplified control system • Cold and vacuum testing on cryogenic equipment • ATEX room inspection • Not populating drag-chains prior to installation with electrical cabling

More Related