1 / 7

Updated Run Plans.

Updated Run Plans. - pre-commissioning - Target, - beamline functionality detectors, particle production decay solenoid - steps towards (6 π ,200) muon beamline. K.Tilley, MICO, 07/02/08.

amandla
Download Presentation

Updated Run Plans.

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Updated Run Plans. • - pre-commissioning- Target, • - beamline functionality • detectors, particle production • decay solenoid • - steps towards (6π,200) muon beamline K.Tilley, MICO, 07/02/08

  2. pre-commissioning : -Beam monitor backgrounds/calib/DAQ -completion of p/s services -DSA entry:- completion of mgt services - polarity(power) from p/s - direct klixon checks(B2,QN) - (klixon) interlock checks - system soak tests – stability/thermal - Synch entry:- polarity(power) from p/s - direct klixon checks (B1 esp, Q1/2/3) - (klixon) interlock checks - system soak tests – esp B1. (1/2hrs) - field at saturation – B1.

  3. Target : - negotiate agreement to activate target.Formal plan. To include:- position reproducibility (shallow dip) flux / beam loss signal reproducibility. Reliability insert towards 38mm &/or 0.05V. Loss v dip. Crude production estimates (using upstream monitor) pre/post activation measurements. Radiation levels in MICE hall. (Tgt only)

  4. Beamline functionality – to exercise beamline slow controls beamline model understanding beamline monitors - poss can overlap with Target work. - poss can overlap with det/DAQ cmsg/p.prodn. - 500MeV/c protons, since best rates - likely reasonable pion flux, albeit <10%. - what will do:-….. Exercise Quads, Diploles, confirm optics. Probe & set alignment MICE Hall radiation levels. - have proton optics (Q1,Q2. triplet in devmt) - Require…triplet lattice, scenarios, alignment simulations & procedure- desire… settings store/restore, B->I programming

  5. Detector calibration – to commission available detectors [Ckov etc] - to shakedown DAQ / MLCR.& particle production [Ckov can disting π+ if run +s] - require to sign off rqd beamlines [difft dE @ each E: air, mtrls etc] & then produce:-example stages:- positive pions [?]: • [ incl protons or high purity pions desired? Thus include proton abs]- Can provide up to ~500MeV/c, quads on. [imperfect but ok workable above 400] • Number of scan points? • negative pions:- • Can provide up to ~500MeV/c, quads on. [imperfect but ok workable above 400]- Number of scan points? • electrons:- - Require new optic @ ~100MeV/c, quads on.

  6. Decay solenoid commissioning - hardware commissioning: cooling. Power. Interlocks. Quench checks etc. Field polarity measurements etc - with beam commissioning:- (using detector on DS end) [beam dynamics from ABl note]

  7. Steps toward 6π muon beamline in Step I Require:- assume all detectors incl TOFs, Tracker available - reconstruction available. pions through whole system @ ~ 280MeV/c: - optimise u/str optics for flux, alignment, spot size DS d/s - d/str beamline with pions ~ 260MeV/c for alignment optics? Scale upstream to ~ 444.7MeV/c - final check of upstream optics. Downstream @ 260MeV/c @ backward decay muons: - backward decay should be aligned. - measure transmission, natural emittance. - calculate rqd matching parameters. - optimise for (6π,200) with optimiser scheme.

More Related