1 / 16

AUTOCLAVE ELECTRICAL FINAL DESIGN REVIEW

AUTOCLAVE ELECTRICAL FINAL DESIGN REVIEW. BY: FRANK JONES DATE: 6/03/03. HEATERS AND EQUIPMENT POWER SYSTEM CONTROL SYSTEM PROCESS RECOVERY SAFETY PHYSICAL DETAILS CONSTRUCTION DETAILS SCHEDULE AND COST. REVIEW OUTLINE. HEATERS AND EQUIPMENT.

Download Presentation

AUTOCLAVE ELECTRICAL FINAL DESIGN REVIEW

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AUTOCLAVEELECTRICAL FINAL DESIGN REVIEW BY: FRANK JONES DATE: 6/03/03

  2. HEATERS AND EQUIPMENT POWER SYSTEM CONTROL SYSTEM PROCESS RECOVERY SAFETY PHYSICAL DETAILS CONSTRUCTION DETAILS SCHEDULE AND COST REVIEW OUTLINE

  3. HEATERS AND EQUIPMENT • 48000 WATTS OF 480V, 1 PH. HEATERS (PRIMARY HEAT) • 24000 WATTS OF 480V, 1 PH. HEATERS (SECONDARY HEAT) • 24000 WATTS OF 480V, 3 PH. PROCESS AIR • 7 1/2 HP BLOWER FOR PROCESS AIR • TWO VACUUM PUMPS FOR VESSEL

  4. POWER SYSTEM • ALL POWER COMES FROM TWO EXISTING 480V RECEPTACLES THAT ARE ON THE SOUTH WALL OF THE TEST CELL. • POWER IS DISTRIBUTED VIA TWO SYSTEM CARTS. ONE 480V AND ONE 208/120V (W/TRANSFORMER)

  5. CONTROL SYSTEM • THE AUTOCLAVE HEATING, VACUUM AND BLOWER SYSTEM ARE ALL CONTROLLED FROM CART #2 (B-ACLV-02). • THERMOCOUPLE METERS WITH VISUAL DISPLAYS & PC INTERFACE ARE AT CART #2 • 480V POWER CONTACTORS AND 480V PANELBOARDS ARE ON CART #1

  6. B-ACLV-02

  7. PROCESS RECOVERY • TIMELY RECOVERY FROM POWER FAILURE OR CRITICAL EQUIPMENT FAILURE ARE ADDRESSED IN SYSTEM DESIGN. • D-SITE DIESEL GENERATOR BACKUP • DEVICE ISOLATION CAPABILITY • EQUIPMENT SUBSTITUTION • CONTROL AND SAFETY SYSTEM ON UPS • PATCH PANEL THERMOCOUPLE INTERFACE

  8. SAFETY • TEST CELL AREA “HIGH TEMPERATURE” WARNING LIGHT/SIGNS • VESSEL GROUND FAULT PROTECTION/ALARM • 480V POWER ISOLATION-LOCKOUT AND TAGOUT DURING VESSEL ACCESS • UPS POWER FOR CRITICAL CONTROL EQUIPMENT • BUILDING STEEL GROUND ALL EQUIPMENT

  9. PHYSICAL DETAILS HEATER PLACEMENT

  10. THERMOCOUPLE PLACEMENT

  11. RACEWAY & EQUIPMENT LAYOUT

  12. CONSTRUCTION DETAILS • VESSEL HEATERS, CONDUIT & WIRING ARE INSTALLED @RESA BLDG. • CART MECH. FABRICATION & ELECTRICAL EQUIPMENT MTD. ON CART @ RESA & SHOP • CONTROL JUNCTION BOX WIRING @ SHOP • VESSEL INTERFACE JUNCTION BOXES WIRED AND INSTALLED @ RESA BLDG. • TEST CELL FABRICATION WILL BE KEPT TO A MINIMUM ex.WIREWAY AND INTERFACE CABLES

  13. COST AND SCHEDULE • EXISTING EQUIPMENT • APPROX. $9000.00 M & S SAVINGS • 2 “OMEGA” PROCESS CONTROLLERS & 2 METERS • 2 VACUUM PUMPS WITH STARTERS • 2-12K WATT HEATER AND PROCESS BLOWER • SIZE-2, 480V STARTER & SIZE-1 208V STARTER • 1- 30 KVA 480-208V TRANSFORMER • MISC. WIRE AND CONNECTORS • NEW EQUIPMENT • $3,900 “OMEGA” EQUIPMENT • $11,000 3-PANELBOARDS, CONTACTORS, WIREWAY, ETC. • TOTAL M & S $14,900

  14. ELECTRICAL CONSTRUCTION MAN DAYS: • •50 MAN DAYS, $30,000 • •TOTAL ELECTRICAL M & S AND LABOR: $44,900 • EARLY START: JUNE 16, 2003 • REQUISITION MATERIALS • START CART FABRICATION AND ELECTRICAL ASSEMBLY • START ELECTRICAL CONTROL AND POWER WIRING • UPON VESSEL DELIVERY START INTERNAL AND EXTERNAL ELECTRICAL • START TEST CELL EQUIPMENT INSTALLATION AND INTERFACE • TEST HEATING CONTROL SYSTEM • TEST VACUUM/HEATING SYSTEM • CALIBRATE AUTOTUNE WITH LOADED VESSEL

More Related