Overview of FDOT’s Long Range Estimating System

2005 TEA Conference. Overview of FDOT’s Long Range Estimating System. November 4, 2005 Daytona Beach, Florida. Presentation Outline. History / Background LRE Basic Concepts Project Levels Typical Sections Demo. History / Background.

arnaud
Download Presentation

Overview of FDOT’s Long Range Estimating System

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 2005 TEA Conference Overview of FDOT’sLong Range Estimating System November 4, 2005 Daytona Beach, Florida

  2. Presentation Outline • History / Background • LRE Basic Concepts • Project Levels • Typical Sections • Demo

  3. History / Background • Pre-1986, we used cost-per-mile method. • In 1986 we developed our first LRE program, which used typical section characteristics, applied to a length of roadway, to generate: • Pay Items • Quantities • Unit Prices • Original LRE didn’t facilitate accurate estimating of non-roadway features.

  4. History / Background • In 2000 we identified a need for a new and improved LRE: • User friendly and intuitive • Minimal input required • Improved accuracy and reporting • Planning team formed in October 2000 to lay the groundwork: • Statewide representation of key estimators • Bi-monthly workshops, Oct 2000 – June 2001 • Established preliminary requirements, developed input screens, formulas, etc., while funding for LRE was pending.

  5. History / Background • Programming team formed in July 2001 • Project Manager • 2 Systems Program Analysts • 4 Programmers / Web Developer • 2 Database Administrators • Programming team and Planning team combined, to form the Functional Steering Committee • Users involved in all phases of the project • Implemented new system in July 2003 

  6. LRE Quantities • Formula-Driven or Calculated Quantities: • Earthwork, Roadway, Median and Shoulder quantities can be generated by a formula • System uses pavement, median and shoulder widths, pavement design information and section length to generate roadway quantities (stabilization, base, asphalt, FC, etc.) • System uses fill height, slope data, and characteristics from other components (roadway, median, shoulder) to generate the appropriate earthwork quantities.

  7. Sample Input Screen

  8. LRE Quantities, continued… • “Component Detail” Default Quantities: • Available on several components • Spreadsheet of assumed pay items, quantities and unit prices • Quantities are based on model selected and length specified (Drainage, Signing, Conventional Lighting, Erosion Control), or a selected type/size (Signalization, Retention Basins, Intersections) • Default data can be adjusted, as necessary.

  9. Sample Component Detail

  10. No Administrative functions Administrative Features • User Maintenance / Role Assignment • *C.O. Administrator (can assign any role) • *District Coordinator (can assign Estimator, Coder and Reviewer roles within their District) • Estimator • Coder • Reviewer (District and State) • Maintenance of Pay Items and Prices • Maintenance of System Defaults (C.O. only) • Typical section default characteristics • Component detail default values • Maintenance of User Help (C.O. only)

  11. LRE Demonstration

  12. Price Files and Updates • Recently changed the update process and schedule. • Default prices will now be updated each month, using 1 year of bid history, and all bidders. • Pricing is entirely customizable.

  13. Technical Information • Web-based (Intranet application) • Oracle database interfaces with: • DSS • FDOT’s Financial Management System / Work Program Administration • Estimates Report Tracking System (ERTS) • No hardware or software requirements, other than standard desktop and access to the FDOT intranet

  14. Overall Success • Management Support • Dedicated resources / personnel • User involvement at ALL phases: • Planning • Requirements • System Design • Construction • Testing • Implementation • User Feedback feature

  15. Post-Implementation • During the first year, 2 major Maintenance Releases addressed over 40 enhancements to the initial implementation. • Now in the system maintenance phase • 43 enhancements completed to date • 25 enhancements pending • Expected to meet the Department’sneeds for at least the next 7-10 years

  16. Contact Information • Dale Stanley, LRE Administrator; User Support and Training 850.414.4197 dale.stanley@dot.state.fl.us • David Davis, Technical Questions 850.410.5467 david.davis@dot.state.fl.us • Greg Davis, Management Issues 850.414.4170 phillipgreg.davis@dot.state.fl.us

  17. Questions ???