An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Conventional Facilities Status Martin Fallier, Conventional Facilities Div. Director Conventional Facilities Advisory Committee Review October 5-6, 2010

  2. Outline Baseline Overview Scope, Cost & Schedule Organization Progress Since Last Review Technical Progress Cost & Schedule Performance Risks Issues Charge Items Recommendation tracking

  3. Baseline Scope WBS 1.5 Conventional Facilities Added Scope 1.5.3.7 HXN Beamline Addition Addition to LOB 3 structure

  4. NSLS-II Site Plan N NSLS-II With Full LOB Build-Out 100 0 200

  5. Ring Bldg Overall Floor Plan LOB 1 Storage Ring & Booster Tunnel Experimental Floor Access Corridor Service Buildings LOB’s 1, 2, & 3 Base Scope Future LOB’s Earth Berm Lobby RF Injection LOB 2 LOB 5 Process Cooling Water Bldg Vehicle Tunnel LOB 4 LOB 3

  6. Ring Building Section

  7. LOB First Floor Plan • 57 One person Offices • Two people Offices • Six people Offices • Wet Laboratories • Dry Laboratories • Machine Shop • Conference Rooms • 1 Loading/Storage Area Total = 38,000 gsf Each Lab = 480 nsf

  8. LOB Exterior Perspectives LOB Roofline LOB Entry

  9. WBS 1.5 Cost Baseline 1 2,3,4 5 Major Increases or changes: Includes added CM staffing (~$0.9M) and holding place for const. safety incentive ($1M) Incorporated cost for larger LOBs after LOB award (~$9M) Incorporated post bid addendum and miscellaneous scope and field changes Incorporated HXN beamline building cost (~$1.6M) Incorporated full data and communication cost in Integrated control, comm & data

  10. CF Schedule

  11. CF Organization

  12. Technical Progress • Ring Building contract Excellent progress, maintaining status on or ahead of schedule • SR Tunnel concrete complete except opening at Pentant 5 • Opening used for interior courtyard access • Experimental Floor complete to Pentant5 • Structural steel complete except opening at P5 and Injection Bldg • Building enclosure, roofing and siding making good progress • Utility system installation nearing completion in interior of ring • Unit substations 6 of 8 are installed, last two in progress • Cooling Tower Building enclosure 95% complete, MEP underway • Mechanical, electrical, plumbing underway in P1, P2, P3, & P4 • Booster and Linac tunnel concrete nearly complete

  13. Technical Progress • Chilled Water Plant Expansion Contract Running on/ahead of schedule • CCWF, Cooling Tower and Pump-house Buildings complete • Equipment installation in all areas nearly complete • Instruments and controls installation underway • Equipment start-up and commissioning to begin in October • Electrical Substation Expansion Contract Running on schedule • Ductbank installed & 15kV switchgear installed in building • 20 MVA transformer delivered, placed & tied-in • Installation of cabling in progress • Major cable pull to NSLS-II site in October

  14. Technical Progress cont’d • Chilled Water Piping Tie-in at central main and NSLS-II site complete • Last section of pipe to be installed and tested this week • Site restoration and contract completion in October • Chilled water available for the site for start-up and commissioning • LOB Construction Contract awarded, mobilization underway • Bonds and insurance received • HASP reviewed and being revised, NTP likely within 1 week • Held Torcon/EW Howell site coordination mtg • Held kick-off and schedule planning mtgs • Submitted HXN Building addition pkg to GC’s for price proposal • Construction underway in October, complete spring of 2012

  15. One Year Ago Photo From BGRR Stack 9-21-09 Vehicle Tunnel SR Tunnel Wall Forms SR Tunnel Slab Status of construction Site at FY09 End

  16. Technical ProgressToday Photo From BGRR Stack 9-20-10 Clg Twr Bldg Booster Tunnel Roof Deck Roof Insulation Finished SSM Roof Opening @ P5 Exterior Siding Lobby Curtain-wall Opening for LOB 1 • SR tunnel and structural steel complete except P5 opening • Roof deck complete, Insulation to P5, Finished SSM Roof at P1 • P1, & 2,Cooling Twr, RF & Compressor Bldg Enclosure all underway • Utility installation ~80% complete in inner courtyard

  17. Technical Progress cont’d • SR Tunnel – Painted, Conduit , Lighting & Ductwork Installed Exterior Siding • Pentant -1 – Ductwork & Piping In Place

  18. Technical Progress cont’d • Injection Bldg Booster Ring Tunnel Vehicle Tunnel Nearly Ready For Use • RF Area Unit Substation

  19. Overall Cost and Schedule Assessment • Cost Assessment: Cumulative cost variance $+2.3M or +1.8% • On budget - CPI =1.02 • Schedule Assessment: Cumulative schedule variance $+5.9M or +4.7% • On or slightly ahead of schedule - SPI =1.05

  20. Variance Analysis • Cost Variance +$2.3M • Temporary positive cost variance due to differences in accrued vs monthly invoiced values • Actual positive cost variance ~ $400k due to miscellaneous small underruns - >91% of remaining work is under fixed price contract • This variance expected to go to zero $ as contracts are closed out • Schedule Variance +$5.6 M • Work in P1 – P5 ahead of plan for concrete, steel, enclosure and mechanical, electrical & plumbing • Work on Cooling Tower & Process Water Systems ahead of plan • Remaining contracts on or close to plan

  21. Risks • Construction Safety - program must continue to be effective • Substantial performance improvement since 9/30/09 accident • Increased number of construction safety engineers to 3, soon to be 4 • Continually working with GC to improve program • Potential for field changes, errors/omissions thru construction • Running ~ 1.5% - see following slide for breakdown of status to date • Potential for design changes from ASD & XFD • Running ~ 1.5% - see following slide for breakdown of status to date • System coordination is now complete – risk reduced • Risks of Ring Bldg GC and LOB GC conflicts • Effective plan and requirements for coexisting on the site

  22. Ring Bldg Contract Change status • As of 9/30/10 will have completed $101M work – 57% • Changes due to approved scope changes or design maturity • $1.58M to date or ~1.5% of work to date • Weekly interface mtgs effective at identifying changes early • Changes due to design errors & omissions • $1.56M to date or ~1.5% of work to date • This includes projected estimate of changes not yet agreed upon • Changes due to existing conditions • Very low at just $130k – no more of these changes likely • Weekly mtg w/GC to expedite resolution of changes

  23. Issues • Continued focus on contractor safety performance is essential • Need to maintain close oversight of detailed contractor schedule activities needed to achieve BORE’s • Engineering staff heavily loaded • Process of resolving and implementing contract changes is labor intensive • Possible added scope from ASD & XFD will add to load • Engineering involvement required for start-up and commissioning Mitigating factors • LOB document submittal/review phase starting up as Ring bldg winds down • Workload should ease soon as CHW and Electric Utility pkgs are completed

  24. Conclusions • CF activities are on budget and on or ahead of schedule • Contractor safety program has improved substantially • Applying lessons learned to LOB safety program • Construction proceeding well • CHW& elect substation winding down – move focus to LOB • LOB mobilization underway and progressing well • Getting ready for equipment start-up and commissioning • On track for 1stRing Bldg beneficial occupancy 2/11 & Ring Bldg construction completion 4/12

  25. Charge Items • Are Conventional Facilities Division’s plans &performance consistent with achieving project cost, schedule, and technical objectives • Covered in multiple status presentations • Are the plans and measures to assure construction worker safety appropriate and effective at minimizing potential for worker injury? • See Ken Krasner Presentation on Construction safety • Are the proper plans, measures and resources in place for effectively managing the coexistence of the Ring Building and LOB contractors on the same construction site? • See Mike Bromfield Presentation on LOB and Ring Bldg GC Coexistance • Are the plans and measures to assume beneficial occupancy of the facilities sufficient to enable orderly installation of accelerator systems and eventual transition to operations? • Covered in multiple presentations on BORE, ASD Installation & Ops planning