An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Undulator Week Installation Discussion April 29th, 2008

  2. Field Personnel • Installation Manager • Mike Zurawel • Safety Oversight • Michael Scharfenstein • UTR • Raimond Cuadrado

  3. Proper Installation Assurance • All work will be reviewed for safety and will not proceed until the WAF has been completed and signed off. • All devices are to be signed off by the responsible parties prior to installation. • Travelers for girder assemblies will be completed and signed off by the responsible groups prior to installation.

  4. Safety Items • There will be a daily tailgate meeting held at 07:00 in building 104C conference room. Every trade must have a representative at the meeting or they will not be allowed to work in the Undulator Hall • Davis Bacon contractor’s lifting and rigging plans to be reviewed and approved by the Hoisting and Rigging Committee prior to commencement of work