240 likes | 346 Views
Undulator Week Installation Discussion April 29 th , 2008. Field Personnel. Installation Manager Mike Zurawel Safety Oversight Michael Scharfenstein UTR Raimond Cuadrado. Proper Installation Assurance.
E N D
Undulator Week Installation Discussion April 29th, 2008
Field Personnel • Installation Manager • Mike Zurawel • Safety Oversight • Michael Scharfenstein • UTR • Raimond Cuadrado
Proper Installation Assurance • All work will be reviewed for safety and will not proceed until the WAF has been completed and signed off. • All devices are to be signed off by the responsible parties prior to installation. • Travelers for girder assemblies will be completed and signed off by the responsible groups prior to installation.
Safety Items • There will be a daily tailgate meeting held at 07:00 in building 104C conference room. Every trade must have a representative at the meeting or they will not be allowed to work in the Undulator Hall • Davis Bacon contractor’s lifting and rigging plans to be reviewed and approved by the Hoisting and Rigging Committee prior to commencement of work