An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Undulator Week Issues C.E. Rago System Integration

  2. Integration Issues • SLAC Earthquake Updates: • Written Report under review prior to SLAC-EC presentation. • DeBarger / Dormiani • Difficulties • SLAC Procedural Adjustments / Pending Upgrades • Design Style, Complete & Integrated Procedures • Uniformity / Efficiency of Installation

  3. Summary • Magnet, Girder, Pedestal System is in compliance with current SLAC Earthquake standards in regards to preservation of functionality. • SLAC-1-720-0A24E-002 with slight modifications • 1997 Uniform Building Code • Caveats: • Formal Earthquake Committee Approval • Installation procedures must support the current ANL design and all manufacturer installation procedures. • Earthquake preloads must be applied, equal to and or greater than the ANL design. • ANL to load tests to failure are run on positioning slides. • Hard Shims, between pedestal and concrete, needs to be analyzed.

  4. Pre-Loads/ Stresses • Foot Plate Connection 1300 in-lbs • Support Plate to Transition 380 in-lbs • Transition Plate to Slide 330 in-lbs • Slide to Girder 300 in-lbs • Girder to Interface 70% Yield

  5. Slide Test • No manufacturing data available on seismic and or similar loads. • M/Mp = 81% (Seismic M / Static Mp) • Mp is about the ‘Z’ axis.

  6. Hard Shims • Current Assumption: • There is no stand-off between anchor plate and the concrete floor. • ANL design • Shims at 6/6 anchors • Grouted Base Plate • Sand filled Pedestal

  7. Concrete Anchors • Assumed Hilti HIT-RE-500-SD Adhesive Anchors. • Current calculation was simplified to use only 4 “outer’ anchors. • Must calculate the effect of 6 anchors per pedestal.

  8. Integration Issues • Integrated Assembly Procedure • Zurawel to Lundahl to Poling • Start from existing ANL procedures. • Zurawel is expanding to cover all field tasks. • Lundahl coordinating alignment. • Metrology dominates assembly-LeCocq & Wolf • Poling will control vacuum, handling, and anything else we need.