Undulator Week 3. Magnet Power Supplies Phase 4 Installation Antonio de Lira Kristi Luchini. Undulator Magnet PS Phase 4 Installation Agenda. Installation Program - Scope Rack Profiles & System Characteristics Overall Schedule Open Items Magnet PS Controls By Kristi Luchini.
E N D
Undulator Week 3 Magnet Power Supplies Phase 4 Installation Antonio de Lira Kristi Luchini
Undulator Magnet PS Phase 4 InstallationAgenda • Installation Program - Scope • Rack Profiles & System Characteristics • Overall Schedule • Open Items • Magnet PS Controls By Kristi Luchini
Undulator Magnet PS – PH4 Installation ProgramOriginal Scope • B913 – UND • 54 MCORs • 18 QUAD – MCOR6 • 36 X/YCOR – MCOR1 – Not part of Phase IV • B921 – UND + DUMP • 45 MCORs • 15 QUAD – MCOR6 • 30 X/YCOR – MCOR1 – Not part of Phase IV • 03 Intermediate PS – DUMP • 06 MCORs – DUMP
54 MCORs - UND 18 QUAD – Phase IV 36 X/YCOR (?) 45 MCORs – UND 15 QUAD – Phase IV 30 X/YCOR (?) 03 Intermediate PS – DUMP 06 MCORs – DUMP Undulator Magnet PS - PH4 Installation Program B913 B921
Undulator Magnet PS Installation Program – B921 03 Intermediate 45 MCORs – UND 06 MCORs - DUMP
Undulator Magnet PS – Electrical Interconnections Undulator magnet PS are NOT interlocked (except for GND fault)
Schedule • Overall Schedule • Magnet PS Cable Plant (Phase 4) Ponce Rodriguez – This review • 01/30/08 Site Visit • 02/19/08 Bid Opening • 03/04/08 Award • 04/01/08 Installation Start • 10/31/08 Installation Complete • Detailed schedule • Integrated with Project Office’s Installation Schedule
Equipment Status / Rack Readiness B913 B921
Open Items • 66 MCORs for UND correctors • MCOR modules to come from PEP • MCOR modules have been requested already • D. MacNair has a new design for a MCOR1 • No performance requirements document • PCD will assume 25 ppm/C is fine Note: Support buildings will have temperature control: 75 ± 5F
Undulator Magnet PS - Controls • Magnet PS Control Systems • Kristi Luchini
Magnet PS ControlsProcurement Status * Equipment within PS racks
Magnet Magnet EPICS IOC MCOR VME Crate System Architecture OPI OPI Ethernet Timing (Fiber Optic) 16 Magnets@ 6 Amps max Note: configure for 1 or 6 A Terminal Server PLC PS Protection System Bulk PS
Software • IP Addresses Network Nodes – Done • Software – Done (for 10Hz feedback) • Databases - April 28 to May 10, 2008 • polynomials (I vs B) as magnets are measured. • Displays • B913: Complete May 5, 2008 • B921: Complete May 10, 2008 • Pre-Installation checkout in B15 • B913: May 10-15, 2008 • B921: May 15-20, 2008 • System Checkout - Network checkout and system integration • B913: Oct 31 - Nov 11, 2008 (54 MCORs), Install racks July 10-15 • B921: Oct 29 – Dec 4, 2008 (45 MCORs), Install racks July 22-30