1 / 22

Undulator Week 3

Undulator Week 3. Magnet Power Supplies Phase 4 Installation Antonio de Lira Kristi Luchini. Undulator Magnet PS Phase 4 Installation Agenda. Installation Program - Scope Rack Profiles & System Characteristics Overall Schedule Open Items Magnet PS Controls By Kristi Luchini.

aretha-knox
Download Presentation

Undulator Week 3

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Undulator Week 3 Magnet Power Supplies Phase 4 Installation Antonio de Lira Kristi Luchini

  2. Undulator Magnet PS Phase 4 InstallationAgenda • Installation Program - Scope • Rack Profiles & System Characteristics • Overall Schedule • Open Items • Magnet PS Controls By Kristi Luchini

  3. Undulator Magnet PS – PH4 Installation ProgramOriginal Scope • B913 – UND • 54 MCORs • 18 QUAD – MCOR6 • 36 X/YCOR – MCOR1 – Not part of Phase IV • B921 – UND + DUMP • 45 MCORs • 15 QUAD – MCOR6 • 30 X/YCOR – MCOR1 – Not part of Phase IV • 03 Intermediate PS – DUMP • 06 MCORs – DUMP

  4. 54 MCORs - UND 18 QUAD – Phase IV 36 X/YCOR (?) 45 MCORs – UND 15 QUAD – Phase IV 30 X/YCOR (?) 03 Intermediate PS – DUMP 06 MCORs – DUMP Undulator Magnet PS - PH4 Installation Program B913 B921

  5. Undulator Magnet PS Installation Program - B913 54 MCORs

  6. Undulator Magnet PS Installation Program – B921 03 Intermediate 45 MCORs – UND 06 MCORs - DUMP

  7. Undulator Magnet PS – Electrical Interconnections Undulator magnet PS are NOT interlocked (except for GND fault)

  8. Schedule • Overall Schedule • Magnet PS Cable Plant (Phase 4) Ponce Rodriguez – This review • 01/30/08 Site Visit • 02/19/08 Bid Opening • 03/04/08 Award • 04/01/08 Installation Start • 10/31/08 Installation Complete • Detailed schedule • Integrated with Project Office’s Installation Schedule

  9. Schedule – B913

  10. Schedule – B921

  11. Equipment Status / Rack Readiness B913 B921

  12. Open Items • 66 MCORs for UND correctors • MCOR modules to come from PEP • MCOR modules have been requested already • D. MacNair has a new design for a MCOR1 • No performance requirements document • PCD will assume 25 ppm/C is fine Note: Support buildings will have temperature control: 75 ± 5F

  13. Undulator Magnet PS - Controls • Magnet PS Control Systems • Kristi Luchini

  14. Magnet PS ControlsProcurement Status * Equipment within PS racks

  15. Magnet Magnet EPICS IOC MCOR VME Crate System Architecture OPI OPI Ethernet Timing (Fiber Optic) 16 Magnets@ 6 Amps max Note: configure for 1 or 6 A Terminal Server PLC PS Protection System Bulk PS

  16. Software • IP Addresses Network Nodes – Done • Software – Done (for 10Hz feedback) • Databases - April 28 to May 10, 2008 • polynomials (I vs B) as magnets are measured. • Displays • B913: Complete May 5, 2008 • B921: Complete May 10, 2008 • Pre-Installation checkout in B15 • B913: May 10-15, 2008 • B921: May 15-20, 2008 • System Checkout - Network checkout and system integration • B913: Oct 31 - Nov 11, 2008 (54 MCORs), Install racks July 10-15 • B921: Oct 29 – Dec 4, 2008 (45 MCORs), Install racks July 22-30

More Related