FMB Lepse Dismantling Project Status . Lepse IPMU. 26 April 2013. Moscow. KEY ACHIEVEMENTS - 1. Lepse has been towed to Nerpa – September 2012. KEY ACHIEVEMENTS - 1. All necessary approvals were obtained prior to the towing operation
E N D
FMB Lepse DismantlingProject Status Lepse IPMU 26 April 2013 Moscow
KEY ACHIEVEMENTS - 1 Lepse has been towed to Nerpa – September 2012
KEY ACHIEVEMENTS - 1 • All necessary approvals were obtained prior to the towing operation • Three tugs were used with the addition of “Rossita” as a support vessel • An Emergency Rescue Group were in attendance • A harbour exclusion zone was set-up • The operation was carried out successfully
KEY ACHIEVEMENTS – 2 • Lepse is now safely moored at Nerpaalongside a temporary berth at the Pier • All physical protection and radiological safety measures are in place, the Sanitary Passand Guardhouse facilities are installed. • Lepse is under constant monitoring
KEY ACHIEVEMENTS - 3 • The Integrated Technical Design has been prepared by Aspect Conversion and is currently being reviewed by FCNRS, Regulators and International Experts. • The contract for the adaptation of Nerpa infrastructure to facilitate the raising of Lepse to the slipway pad is close to signature. • The Tender for the process equipment is under preparation.
PROJECT STRUCTURE LEPSE PROJECT • Work to Completion NDEP AREA 1 – Project Management AREA 2 – Development of Technical Documentation AREA 5 – Lepse Dismantling SNF & RAW Handling SNF Transport to Mayak LSP Transport to Saida Bay AREA 4 – Improvement of Nerpa Infrastructure AREA 3 – Preparation for Defuelling Extract from Procurement Plan rev ’C’