90 likes | 294 Views
Rational Team Concert 2.0.0.1 SVT Kickoff July 22, 2009. ISL Manjunathan Nipun Sachin. CDL Jian Qiu Lin. RTP, USA Anu Ken Sanjay. Lexington, USA Carol Cindy Karen Ken Manju Mark Olga Sentella Sujana. Located around the world, but ONE team!. There is someone in SVT testing
E N D
ISL • Manjunathan • Nipun • Sachin • CDL • Jian Qiu • Lin • RTP, USA • Anu • Ken • Sanjay • Lexington, USA • Carol • Cindy • Karen • Ken • Manju • Mark • Olga • Sentella • Sujana Located around the world, but ONE team! There is someone in SVT testing RTC 24 hours a day!
Who are we? • Anu – Performance Lead • Carol – CC Bridge, Enterprise Deployment Scenario • Cindy – Release Manager • Jian Qiu – Benchmark • Karen – Test Coordinator • Ken McClamroch– SVT Test Architect • Ken Sandler – Automation development • Lin – SVT Manager – Benchmark team • Manju – Performance, Integration Project • Manjunathan –IPv6 Scenario, RTC.net Scenario • Mark – Technical Lead • Nipun – RTC.net Scenario, Co-existence Scenario • Olga – End-to-End Solutions Scenario, RQM Internal Deployment • Sachin – ISL Lead • Sentella – Performance • Sujana – CQ Importer, Mainsoft Lead , Integration Project
Themes for 2.0.0.1 • We are one team • Communicate, communicate, communicate • Talk to each other • Be tolerant of different communication styles • Sustainable pace • Realistic estimates, realistic plan, execute to plan • Don’t take on additional tasks without talking to Cindy and Karen first (before you commit) • Done, done, done • What does done mean? • Complete all aspects of a task: • RQM – points, test execution records • Communicate the completion – email, update the workitem, Assessment report • Analysis • Posting results • Clean up the machine • Practice the process
2.0.0.1 Purpose and Schedule • This plan is for a minor release of Rational Team Concert. • The primary focus of this release is to: • enable sales accelerators • continued enterprise deployments of Rational Team Concert by enhancing performance and scalability
Process • Analyze content • Plan DCP, Plan Items, Enhancements/Features/Defects • Integration Points, Co-existence • Consumabilty • Green Threads • Communicate • Planning • CTP • Using RQM • Test prep tasks • Test plans, test cases – using templates • Test case review/approval – use RQM • Consumability worksheet • Communicate
Process (cont.) • Execution • Take notes for Assessment report • Enter defects early and often (use tags) • Escalate to Karen/Cindy/Development when appropriate • RQM – test points updated, test execution records to track progress • Communicate • Done, done, done • Complete analysis and post results (performance) • Assessment report • Customer Collateral • Communicate
Team Survey… What meetings are there? Ones we know about… • SVT Team meetings • Performance (with PRT) • Jazz Integration • Weekly status (with Albert) • CFT • RTC Development Planning meetings Are there others? • Send information to Karen