Perhitungan

PT. Jebi menerima kontrak untuk membangun sebuah kompleks perumahan pada tanggal 1 Pebruari 2005 yang diperkirakan akan selesai dalam waktu 2 ½ tahun dengan harga kontrak Rp30.000.000, data lain yang diketahui adalah sebagai berikut:. Perhitungan. 2005 Harga Kontrak Rp30.000.000

berke
Download Presentation

Perhitungan

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PT. Jebi menerima kontrak untuk membangun sebuah kompleks perumahan pada tanggal 1 Pebruari 2005 yang diperkirakan akan selesai dalam waktu 2 ½ tahun dengan harga kontrak Rp30.000.000, data lain yang diketahui adalah sebagai berikut:

  2. Perhitungan • 2005 Harga Kontrak Rp30.000.000 Taksiran Biaya: Dikeluarkan tahun 2005 Rp 7.000.000 Taksiran Biaya Penyelesaian Rp20.000.000Rp27.000.000 Rp 3.000.000 Taksiran Laba untuk Th 2005: = 777.780

  3. Perhitungan • 2006 Harga Kontrak Rp30.000.000 Taksiran Biaya: Dikeluarkan tahun 2005&2006 Rp18.000.000 Taksiran Biaya Penyelesaian Rp 9.200.000Rp27.200.000 Rp 2.800.000 Taksiran Laba untuk Th 2005 & 2006: = 1.852.940 Laba tahun 2005 = 777.780 Laba Tahun 2006 =1.075.160

  4. 2007 Harga Kontrak Rp30.000.000 Jumlah Biaya: Tahun sd 2006 Rp18.000.000 Tahun 2007 Rp 9.300.000Rp27.300.000 Rp 2.700.000 Laba Tahun 2005 Rp 777.780 Laba Tahun 2006 Rp 1.075.160Rp 1.852.940 Laba tahun 2007 Rp 847.060