1 / 15

Week 3

Week 3. Electrical. Code 1. all electrical outlets run off a pigtail from main line 2. Each Circuit is wired directly into circuit panel - no junction boxes 3. Bathrooms must have GFCI either at panel or first outlet must be GFCI. 4. In rooms must have outlet a) on any wall longer than 2’

boyd
Download Presentation

Week 3

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Week 3

  2. Electrical • Code • 1. all electrical outlets run off a pigtail from main line • 2. Each Circuit is wired directly into circuit panel - no junction boxes • 3. Bathrooms must have GFCI either at panel or first outlet must be GFCI

  3. 4. In rooms must have outlet • a) on any wall longer than 2’ • b) no more than 6’ from any door • c) no more than 12 feet apart along wall • d) less than 18” off floor

  4. 5. Kitchen • a) Refridgerator on own circuit • b) at least two circuits for outlets • c) must have outlet on island if more than 6 sq ft • d) outlets within 6 feet of sink must be GFCI • e) all countertops must have a wall outlet

  5. 6. Must have at least 1 outside outlet - GFCI • 7. Don’t forget furnace • 8. Fire detectors must be hard wired into a circuit with lights

  6. 9. Separate circuits for: Clothes Dryer, Electric Range, Electric Ovens, Electric Hot Water Heater, Gas Range, Electric baseboard heaters • 10. Must fill all holes between floors with a fire stop caulk • Know local code - does all wiring have to be in conduits?

  7. Plumbing • 1. All drain pipes must be vented • 2. Sewer pipe must be PVC Schedule 40 or better - can use cast iron pipe • 3. All sewer pipe joints must be welded • 4. Minimum 3” pipe for toilets and main runs

  8. 5. Minimum 1-1/4” pipe for sink drains • 6. 1/2” pipe minimum for water pipes type L copper • 7. 3/4” copper pipe for baseboard heat

  9. 8. Gas is piped through Black Iron pipe and fittings or rolled copper tube • 9. boilers and hot water heaters must have a pressure relief valve and piping to floor • 10. Rough in plumbing includes setting tubs and showers - need to insulate outside walls before they are installed

  10. Large Projects • Estimated differently than other projects • Many involve several separate construction projects • May be large area • Roadway • Super Walmart • Large housing development • Have to look at project to do estimate correctly

  11. May break project into quadrants or sections to facilitate scheduling (allows faster completion) • Need to estimate each section to get correct quantities • Won’t be the same quantities as if doing 1 estimate

  12. Contingencies • What is it? • Risk factor • Allows contractor to factor in the unknown • The less that is known about project – higher the contingency • Design –Build has a high contingency at start of project • decreases as project is built

  13. Why do you want to minimize it? • Part of bid • Drives up final price • Need a good estimate • Contingency never equals zero • Always something that is not known • Price fluctuation • Weather • Labor

  14. Mobilization • How much does a piece of equipment cost • Need to include getting it to/from site • Need a truck to haul each way • Each time equipment is brought on site cost money • Want to minimize – how • What is cost? • Truck, driver, setup, inspection • May need equipment to set up

  15. Unit price bid • We have been talking about a lump sum estimate • Unit Price estimate gives price per unit to do work • Multiply units by price to get cost • Still need a good estimate to find errors • Includes all costs associated with item • Mob/Demob, material cost, labor cost

More Related