1 / 11

Project Update: Airport Freeway, I-820 and I-35W

Project Update: Airport Freeway, I-820 and I-35W Townhall Meeting for State Representatives Stephanie Klick and Jonathan Stickland Monday, May 12. Project Overview. Rebuilding existing general purpose lanes Improving/expanding frontage roads Adding TEXpress lanes. Project Benefits.

brigid
Download Presentation

Project Update: Airport Freeway, I-820 and I-35W

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Update: Airport Freeway, I-820 and I-35W Townhall Meeting for State Representatives Stephanie Klick and Jonathan Stickland Monday, May 12

  2. Project Overview • Rebuilding existing general purpose lanes • Improving/expanding frontage roads • Adding TEXpress lanes

  3. Project Benefits • Improved mobility along the most congested corridors in Texas • Road capacity nearly doubled • Reconstructed main lanes (free) • Expanded frontage roads • Four new managed toll lanes (two in each direction) • Managed lane network to extend from North Dallas to downtown Fort Worth

  4. Economic Impact • 2,100 workers along the corridor • 160 companies • 190+ DBE contract awards • $1.299 billion spent on construction • $1.5 million spent per day (avg.) • Spurring new economic development throughout corridor New Outback Steakhouse in Hurst

  5. Operations & Maintenance • Ordinary maintenance, cleaning and mowing • Assistance to motorists in need • Snow and ice removal • Incident response

  6. Segments 1 & 2 Airport Freeway & Loop 820 PROGRESS • Project is approximately 90% completed • Roadway will open in late 2014 – six months ahead of schedule • Opened new WB Grapevine Hwy. 26 on-ramp • Re-opened EB Iron Horse on-ramp • Re-opened WB Iron Horse off-ramp • Re-opened EB off-ramp to Industrial Blvd. • Final pavement placed along eastbound and westbound frontage roads Central Dr. to Murphy Dr./Westpark Way Beach Street Riverside Drive bridge

  7. Segments 1 & 2 Airport Freeway & Loop 820 UPCOMING ACTIVITY • Placing final layers of asphalt along main lanes and frontage roads • NOTE: Traffic shifted to TEXpress lanes between Grapevine Hwy. 26 and Riverside Dr. in June • Opening final configuration of Brown Trail • Opening final configuration of Forest Ridge Dr. • Opening new eastbound Brown Trail on-ramp Brown Trail SH 121/183 Split

  8. Segments 1 & 2 Airport Freeway & Loop 820 FINAL CONFIGURATION This map can be found at www.NTETEXpress.com

  9. I-35W Today

  10. Segment 3A I-35W – Downtown Fort Worth to I-820 interchange (6.5 miles) PROGRESS • Official groundbreaking: May 1 • Right-of-way acquisition underway • Pre-construction work started • Geotechnical surveys being completed • Start heavy construction in 3Q 2014; complete in 2018 • Existing main lanes, frontage roads, interchanges, bridges, ramps and overpasses will be reconstructed • New TEXpressLanes added in both directions • Segment 3B construction underway

  11. Questions? Project Website: www.NorthTarrantExpress.com Information Hotline: 1-888-NTE-2015 Follow us on Twitter: @NTExpress Like us on Facebook: NorthTarrantExpress April is National Distracted Driving Awareness Month; please do not text and drive!