120 likes | 317 Views
WEL-COME TO. RSRDC Ltd. UNIT-I, JAIPUR. ORGANISATION CHART OF RSRDC UNIT –I, JAIPUR. Financial Work Load in Unit-I, Jaipur. Rs. In Lacs. POLICE HOUSING SCHEME. No. of Quarters : 256 Nos. Total Cost : 1499.00 lacs Location : Darbar School, Jaipur Date of Start : July,2007
E N D
WEL-COME TO RSRDC Ltd. UNIT-I, JAIPUR
Financial Work Load in Unit-I, Jaipur Rs. In Lacs
POLICE HOUSING SCHEME No. of Quarters : 256 Nos. Total Cost : 1499.00 lacs Location : Darbar School, Jaipur Date of Start : July,2007 Stipulated Date of Completion : Sept,2009 Expenditure till Date : 1297.00 lacs Likely Completion date : Completed Bottlenecks if any :
Name of Work : Hostel Block at SIHFW, Jaipur Total Cost : 79.84 lacs Location : Jhalana, Jaipur Date of Start : 03.03.09 Stipulated Date of Completion : 02.02.10 Expenditure till Date : 19.80 lacs Likely Completion date : 31.12.09 Bottlenecks if any : nil
Name of Work : Training Hall at State Institute of Helth & Family Welfare Jaipur Total Cost : 100.00 lacs Location : Jhalana, Jaipur Date of Start : 06.03.09 Stipulated Date of Completion : 05.02.10 Expenditure till Date : 15.84 lacs Likely Completion date : 05.02.2010 Bottlenecks if any : nil
Name of Work : Adm. Building, Police out post Jamdoli Total Cost : 11.00 lacs Location : Jamdoli Date of Start : 8.06.09 Stipulated Date of Completion : 7.10.09 Expenditure till Date : 6.61 lacs Likely Completion date : 15.12.09 Bottlenecks if any :
Name of Work : Fencing work at Biological Park, Nahargarh, Jaipur Total Cost : 70.69 lacs Location : Nahargarh, Jaipur Date of Start : 22.06.09 Stipulated Date of Completion : 21.10.09 Expenditure till Date : 42.35 lacs Likely Completion date : 31.12.09 Bottlenecks if any : Work was allotted in two Phase I-Phase completed II-phase is in progress which was awarded in Aug,09
Name of Work : Training Hall at State Institute of Helth & Family Welfare Jaipur Total Cost : 100.00 lacs Location : Jhalana, Jaipur Date of Start : 06.03.09 Stipulated Date of Completion : 05.02.10 Expenditure till Date : 15.84 lacs Likely Completion date : 05.02.2010 Bottlenecks if any : nil
Name of Work : Cyber Lab, Jaipur Total Cost : 25.00 lacs Location : Jaipur Date of Start : 1.08.09 Stipulated Date of Completion : 31.01.2010 Expenditure till Date : 5.60 lacs Likely Completion date : 31.01.10 Bottlenecks if any : nil