150 likes | 317 Views
RSRDC. UNIT- II, AJMER. ORGANISATION CHART OF RSRDC UNIT-II, AJMER. P.K.Arora. Vacant (Addl. Charge to Sh. Sunil jain. ARE. Sh. Lokesh Gupte Sh. Lalit Sharma. 3. Sh. Ashish Sharma 4. Sh. Harsh Rai. Financial Work Load in Unit. Rs. In Lacs.
E N D
RSRDC UNIT- II, AJMER
ORGANISATION CHART OF RSRDC UNIT-II, AJMER P.K.Arora Vacant (Addl. Charge to Sh. Sunil jain ARE • Sh. Lokesh Gupte • Sh. Lalit Sharma • 3. Sh. Ashish Sharma • 4. Sh. Harsh Rai
Financial Work Load in Unit Rs. In Lacs
Important Works Completed during last 5 years Regional Pollution Control Board office, Bhilwara Completion Cost – Rs. 23.97 lacs
Construction of ROB at Kishangarh, Ajmer Total Cost : Rs. 10.00 Crores Location : Kishangarh, Ajmer Date of Start : 18.03.2007 Stipulated Date of Completion : 17.01.2008 Expenditure till Date : Rs. 843.96 Lacs Likely Completion date : 30.6.2010 (Depends on Railway work) Bottlenecks if any : Two nos span and finishing dependant on railway work Status of railway work : Sub structure work completed. Idle since last six months due to finalisation of drawing & design of super structure.
Construction of ROB at Saradhna, Ajmer Total Cost : Rs. 10.00 Crores Location : Beawar road, Ajmer Date of Start : 17.07.2007 Stipulated Date of Completion : 16.06.2008 Expenditure till Date : Rs. 783.56 Lacs Likely Completion date : 31.12.2010 (Depends on Railway work) Bottlenecks if any : Gap slab connecting rly. portion and finishing dependant on railway work Status of railway work : Lay out & shifting of cable work in progress.
Construction of ROB at Bhilwara(UIT Work) Total Cost : Rs. 20.86 Crores Location : Bhilwara Date of Start : 18.03.2007 Stipulated Date of Completion : 17.11.2007 Expenditure till Date : Rs. 1327.31 lacs + Rs385.00 lacs (Rly.) Likely Completion date : 31.05.2010 (Depends on Railway work) Bottlenecks if any : Two nos span and finishing dependant on railway work Status of railway work : Sub structure work completed. Super structure work in progress.
Construction of ROB at Mandal (Bhilwara) Total Cost : Rs. 10.00 Crores Location : Mandal, Bhilwara Date of Start : 19.07.2007 Stipulated Date of Completion : 18.06.2008 Expenditure till Date : Rs. 870.46 Lacs Likely Completion date : 30.06.2010 (Depends on Railway work) Bottlenecks if any : Two nos span and finishing dependant on railway work Status of railway work : Sub structure work in progress.
Construction of ROB at Makrana Distt. - Nagour) Total Cost : Rs. 10.00 Crores Location : Makrana, (Distt.-Nagour) Date of Start : 23.08.2008 Stipulated Date of Completion : 22.07.2009 Expenditure till Date : Rs. 390.67 lacs. Likely Completion date : 30.09.2010 (Depends on Railway work) Bottlenecks if any : Shifting of electric lines & encroachments. Status of railway work : Work order placed. Work yet not started.
Construction of ROB at Nagour Total Cost : Rs. 13.00 Crores Location : Nagour Date of Start : 21.08.2008 Stipulated Date of Completion : 20.07.2009 Expenditure till Date : Rs. 405.45 lacs. Likely Completion date : 30.09.2010 (Depends on Railway work) Bottlenecks if any : - Status of railway work : Work order issued. Work yet not started.
Construction of ROB at Dholpur Total Cost : Rs. 10.00 Crores Location : Dholpur Date of Start : 17.11.2007 Stipulated Date of Completion : 16.10.2008 Expenditure till Date : Rs. 609.36 lacs. Likely Completion date : 30.09.2010 (Depends on Railway work) Bottlenecks if any : - Status of railway work : Work order issued. Work yet not started.
Construction of ROB at Mania-Marena Road Total Cost : Rs. 10.00 Crores Location : Mania, Dholpur Date of Start : - Stipulated Date of Completion : - Expenditure till Date : Rs. 0.03 lacs. Likely Completion date : Bottlenecks if any : The present LC No. 472 is a part of Bye pass for ROB at LC No. 463. Hence traffic is to be bye passed at LC No. 473 which requires interlocking. Railway has agreed for interlocking & up gradation. Which shall be completed by Feb-2010. Revised A&F required amounting to Rs. 16.15 Crore Estimate Submitted to CE PWD through ACE Zone Bharatpur Status of railway work : Revised GAD pending at Railway part for approval, likely to be received in Dec. 2009’