RSRDC. UNIT - KOTA. ORGANISATION CHART OF RSRDC - UNIT KOTA. Financial Work Load in Unit. Important Works Completed during last 5 years. RAJASTHAN TECHNICAL UNIVERSITY, KOTA. Completion cost – 798.00 lacs Foundation Stone laid by Hon’ble Chief Minister on 26.01.2007
E N D
RSRDC UNIT- KOTA
Important Works Completed during last 5 years RAJASTHAN TECHNICAL UNIVERSITY, KOTA Completion cost – 798.00 lacs Foundation Stone laid by Hon’ble Chief Minister on 26.01.2007 Completed in June- 2009
Important Works Completed during last 5 yearsKOTA UNIVERSITY, KOTA • Completion cost – 1086.10 lacs • Foundation Stone laid by Hon’ble Governer of Rajasthan on 21.04.06 & Inaugurated by Hon’ble Education Minister on dated 18.06.08
Important Works Completed during last 5 yearsRFSL BUILDING,KOTA • Completion cost – 220.00 lacs • Completed in year - 2006
POLICE HOUSING SCHEME No. of Quarters : 76 Nos. (16 USQ+60 LSQ) Total Cost : 429.75 Crores Location : Police line, Baran road, Kota Date of Start : 14.05.08 Stipulated Date of Completion : 13.04.09 Expenditure till Date : 394.35 Likely Completion date : 25.12.09 Bottlenecks if any : No. Note: Bar Chart of Important works may also be attached
Name of Work: ROB Morak L C No. 87 Total Cost : 18.08 Crores Location : Near Morak Dabadeh R. Mandi Date of Start : 15.10.08 Stipulated Date of Completion : 31.10.10 Expenditure till Date : 133.38 lacs Likely Completion date : Dec. 2010 Bottlenecks if any : LA completed in Nov.2009 Revised drawing under approval from Railway
POLICE CHOWKI JAGPURA Total Cost : 11.00 Lacs Location : Jagpura Date of Start : 24.06.09 Stipulated Date of Completion : 23.12.09 Expenditure till Date : 3.35 Lacs Likely Completion date : Dec. 2009 Bottlenecks if any : Delay in drawing finalisation.
BOUNDRY WALL OF UMMEDGANJ,KOTA Total Cost : 220.00 Lacs Location : Ummedganj (Kaithoon road) Date of Start : 10.10.08 Stipulated Date of Completion : 09.09.09 Expenditure till Date : 159.59 Lacs Likely Completion date : Jan.,2010 Bottlenecks if any : Delay due to seepage.
TRANSIT HOSTLE RANGE HEAD QTR KOTA Total Cost : 30.00 Lacs Location : KOTA Date of Start : 16.07.09 Stipulated Date of Completion : 15.01.10 Expenditure till Date : 1.02Lacs Likely Completion date : Feb.2010 Bottlenecks if any : No