An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RSRDC UNIT- KOTA

  2. ORGANISATION CHART OF RSRDC - UNIT KOTA

  3. Financial Work Load in Unit

  4. Important Works Completed during last 5 years RAJASTHAN TECHNICAL UNIVERSITY, KOTA Completion cost – 798.00 lacs Foundation Stone laid by Hon’ble Chief Minister on 26.01.2007 Completed in June- 2009

  5. Important Works Completed during last 5 yearsKOTA UNIVERSITY, KOTA • Completion cost – 1086.10 lacs • Foundation Stone laid by Hon’ble Governer of Rajasthan on 21.04.06 & Inaugurated by Hon’ble Education Minister on dated 18.06.08

  6. Important Works Completed during last 5 yearsRFSL BUILDING,KOTA • Completion cost – 220.00 lacs • Completed in year - 2006

  7. POLICE HOUSING SCHEME No. of Quarters : 76 Nos. (16 USQ+60 LSQ) Total Cost : 429.75 Crores Location : Police line, Baran road, Kota Date of Start : 14.05.08 Stipulated Date of Completion : 13.04.09 Expenditure till Date : 394.35 Likely Completion date : 25.12.09 Bottlenecks if any : No. Note: Bar Chart of Important works may also be attached

  8. Name of Work: ROB Morak L C No. 87 Total Cost : 18.08 Crores Location : Near Morak Dabadeh R. Mandi Date of Start : 15.10.08 Stipulated Date of Completion : 31.10.10 Expenditure till Date : 133.38 lacs Likely Completion date : Dec. 2010 Bottlenecks if any : LA completed in Nov.2009 Revised drawing under approval from Railway

  9. POLICE CHOWKI JAGPURA Total Cost : 11.00 Lacs Location : Jagpura Date of Start : 24.06.09 Stipulated Date of Completion : 23.12.09 Expenditure till Date : 3.35 Lacs Likely Completion date : Dec. 2009 Bottlenecks if any : Delay in drawing finalisation.

  10. BOUNDRY WALL OF UMMEDGANJ,KOTA Total Cost : 220.00 Lacs Location : Ummedganj (Kaithoon road) Date of Start : 10.10.08 Stipulated Date of Completion : 09.09.09 Expenditure till Date : 159.59 Lacs Likely Completion date : Jan.,2010 Bottlenecks if any : Delay due to seepage.

  11. TRANSIT HOSTLE RANGE HEAD QTR KOTA Total Cost : 30.00 Lacs Location : KOTA Date of Start : 16.07.09 Stipulated Date of Completion : 15.01.10 Expenditure till Date : 1.02Lacs Likely Completion date : Feb.2010 Bottlenecks if any : No

  12. Proposed New Works

  13. Thankyou