RSRDC. UNIT-IV, JAIPUR. ORGANISATION CHART OF RSRDC UNIT –IV, JAIPUR. Financial Work Load in Unit-IV, Jaipur. Rs. In Lacs. Important Works Completed during last 5 years. Corporate Bhawan, JAIPUR. Completion Cost – Rs. 10.00 Crs.

shae
Download Presentation

RSRDC

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RSRDC UNIT-IV, JAIPUR

  2. ORGANISATION CHART OF RSRDC UNIT –IV, JAIPUR

  3. Financial Work Load in Unit-IV, Jaipur Rs. In Lacs

  4. Important Works Completed during last 5 years Corporate Bhawan, JAIPUR Completion Cost – Rs. 10.00 Crs. Inaugurated by Hon’ble Minister of Corporate Affairs on 22.02.09.

  5. Important Works Completed during last 5 years New Hospital Block,Chark Bhawan, JAIPUR Completion Cost – Rs. 9.10 Crs. Inaugurated by Hon’ble Chief Minister Rajasthan on 30.03.2008

  6. Important Works Completed during last 5 years Double storey Basement Parking, SMS hospital, JAIPUR Completion Cost – Rs. 5.90 Crs. Inaugurated by Hon’ble Chief Minister Rajasthan on 08.12.2007

  7. Important Works Completed during last 5 years 12 nos LSQ at Shiprapath Thana, JAIPUR Completion Cost – Rs. 70.24 lacs

  8. POLICE HOUSING SCHEME No. of Quarters : 112 Nos. LSQ Total Cost : Rs. 654.00 lacs Location : RPA Shastri Nagar Date of Start : 01.03.08 Stipulated Date of Completion : 31.01.09 Expenditure till Date : 549.10 lacs Likely Completion date : 15.12.09 Bottlenecks if any : Electric work & water supply from sousce to be connected

  9. POLICE HOUSING SCHEME No. of Quarters : 24 Nos. LSQ & 12 Nos USq Total Cost : Rs. 288.76 lacs Location : Banipark Thana campus, Jaipur Date of Start : 19.09.08 Stipulated Date of Completion : 18.06.09 Expenditure till Date : 84.63 lacs Likely Completion date : USQ will completed 31.12.09 12 nos LSQ 31.03.03 Bottlenecks if any : Land for 12 nos USQ allotted on 23.10.08 & order of 12 nos LSQ given on 03.06.09 and land for 12. LSQ still awaiting

  10. POLICE HOUSING SCHEME No. of Quarters : 196 Nos. LSQ Total Cost : Rs.311.11 lacs Location : Jail Building Karauli Date of Start : 7.12.06 Stipulated Date of Completion : 06.11.07 Expenditure till Date : Rs. 247.79 lacs Likely Completion date : 30.12.09 Bottlenecks if any : water supply line to be provided & water supply shall be provided by PHED after laying 4.00 Km length pipe line from Karauli so revised estimate submitted for Rs. 428.00 lacs by PHED

  11. POLICE HOUSING SCHEME No. of Quarters : Adm Block, 100 men barracks, 4 nos LSQ & 2 nos USQ Total Cost : Rs. 258.50 lacs Location : Police line and Adm Block Karauli Date of Start : 29.12.07 Stipulated Date of Completion : 28.11.08 Expenditure till Date : Rs. 158.50 lacs Likely Completion date : 30.01.10 Bottlenecks if any : water supply shall be provided by PHED after laying 4.00 Km length pipe line from Karauli

  12. POLICE HOUSING SCHEME No. of Quarters : 12 nos USQ Total Cost : Rs 119.57 lacs Location : Mansarovar Thana, Jaipur Date of Start : 07.07.08 Stipulated Date of Completion : 06.04.09 Expenditure till Date : Rs. 97.42 lacs Likely Completion date : 15.12.09 Bottlenecks if any :

  13. POLICE HOUSING SCHEME No. of Quarters : 12 Nos. USQ Total Cost : Rs. 120.58 lacs Location : Pratapnagar Thana campus, Jaipur Date of Start : 10.09.08 Stipulated Date of Completion : 09.06.09 Expenditure till Date : Rs. 103.51 lacs Likely Completion date : 15.12.09 Bottlenecks if any :

  14. Name of Work : ROB Dausa Total Cost : 10.00 Crores Location : Dausa city Date of Start : 2.09.08 Stipulated Date of Completion : 24.09.10 Expenditure till Date : 129.00 lacs Likely Completion date : December -10 Bottlenecks if any : Estimate was Revised due to increasing number of viaduct as per demand of public representative. Revised estimate of Rs. 2020.00 lacs send to CE PWD vide Addl. Chief PWD Zone – I, Jaipur letter no 2330 dt 5.11.09 Note: Bar Chart for complete work shall be prepared after receiving of Revised A&F sanction

  15. 2. Construction of ROB Gangapur • Total Cost : 10.00 Crores • Location : Gangapur city • Date of Start : 1.04.08 • Stipulated Date of Completion : 28.02.09 • Expenditure till Date : 129.00 lacs • Likely Completion date : April -10 • Bottlenecks if any : Estimate was Revised as bearing capacity is less to provide masonry retaining wall so RCC wall is proposed. Revised estimate of Rs. 1676.00 lacs send to CE PWD vide Addl. Chief PWD Zone – II, Jaipur letter no 2689 dt 27.10.09 • Note: Bar Chart for complete work shall be prepared after receiving of Revised A&F sanction