PEP-II B-Factory Operations and Downtime Planning

PEP-II B-Factory Operations and Downtime Planning. John Seeman Head of the Accelerator Department SLAC Operations Review June 16, 2004. Scheduling. Accelerator Run Planning is done with: Laboratory Director (J. Dorfan) Associate Director of Technical Division (J. M. Paterson)

cachez
Download Presentation

PEP-II B-Factory Operations and Downtime Planning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PEP-II B-Factory Operations and Downtime Planning John Seeman Head of the Accelerator Department SLAC Operations Review June 16, 2004

  2. Scheduling • Accelerator Run Planning is done with: • Laboratory Director (J. Dorfan) • Associate Director of Technical Division (J. M. Paterson) • Assistant Director of Technical Division (J. Seeman) • PEP-II Run Coordinator (U. Wienands) • BaBar Spokesman (M. Giorgi) • BaBar Technical Coordinator (W. Wisniewski) • BaBar Run Coordinators (S. Luitz, U. Nauenberg) • Technical staff • Power Manager (G. Loew) • Operations Head (R. Erickson) • Spokespersons of other small experiments.

  3. AIP funding has driven PEP-II luminosity increases!

  4. Projects reviews for Tech. Div. Projects • Project Review Schedule • Location: POM-FLORA Conference Room Bldg 280. • June 2 No meeting due to DOE review • June 9 Support tube insertion upgrade S. Metcalfe • PEP-II new IP Q2R chamber S. Metcalfe • New low group delay woofer D. Teytelman • HER power supply upgrades for higher tunes U. Wienands • June 16 No meeting due to PEP-II Operations Review • June 23 Vacuum work for HER9 and LER4 RF stations D. Kharakh • Linac Sector 19 accelerator changes for LCLS L. Bentson • Linac Sector 19 shield wall changes for LCLS J. B. Folger • PEP-II LER SLM K. Jobe / A. Fisher • June 30 Power PC upgrades J. Dusatko • Status LER4 and HER9 RF Stations P. McIntosh/A. Hill • Status LER5 and HER10 RF Stations P. McIntosh/A. Hill • New SLAC BFK klystrons and CPI repairs C. Pearson/S. Gold • RF window (476 MHz) production P. McIntosh/C. Pearson • July 7 PEP-II new radial ion pumps D. Wright • PEP-II new IP B1/Q2 chambers J. Langton • PEP-II new IP Q4 and Q5 chambers R. Pope • PEP-II new luminosity chamber A. Sheng • PEP-II new Q2 bellows N. Kurita • July 14 PEP-II new longitudinal FB kicker project U. Wienands • Transverse feedback upgrades U. Wienands • New X-Y BPMs for all of PEP-II R. Johnson • Support tube chiller upgrade S. Ecklund • July 21 New PEP-II injection kicker pulsers A. Kulikov/C. Pappas • PEP-II IR2 power supply upgrades P. Bellomo

  5. SLAC Operating Schedule E164, E164X - Plasma Wakefield Experiment E 165 - FLASH, Flourescence from Air Showers SPPS - Sub pico second X-ray Source

  6. Linac Beam Schedule in Addition to PEP-II

  7. Projected Delivered Luminosity in PEP-II • Delivered Cumulative • Year Month Days Average Peak Integrated delivered • to Peak luminosity luminosity integrated • Luminosity xE33 per period luminosity • Ratio (at end) fb-1 fb-1 • 2004 April 30 0.60 8.5 14.1 210.0 • 2004 May 31 0.60 9.0 14.1 224.1 • 2004 June 30 0.60 9.5 14.4 238.4 • 2004 July 31 0.57 10.0 14.9 253.3 • 2004 Aug-Sept 81 0.00 0.0 0.0 253.3 • 2004 October 10 0.30 6.0 0.8 254.1 • 2004 November 30 0.45 10.0 9.3 263.4 • 2004 December 22 0.55 11.0 11.0 274.4 • 2005 January 25 0.55 11.0 13.1 287.5 • 2005 February 28 0.60 12.0 16.7 304.2 • 2005 March 31 0.60 13.0 20.1 324.3 • 2005 April 30 0.60 14.0 21.0 345.3 • 2005 May 31 0.60 15.0 23.3 368.6

  8. PEP-II Delivered Luminosity (Cont) • 2005 June 30 0.60 15.0 23.3 391.9 • 2005 July-Dec 183 0.00 0.0 0.0 391.9 • 2006 January 25 0.30 9.0 2.9 394.8 • 2006 February 28 0.50 14.0 13.9 408.7 • 2006 March 31 0.55 15.0 21.4 430.1 • 2006 April 30 0.60 16.0 24.1 454.2 • 2006 May 31 0.60 17.0 26.5 480.7 • 2006 June 30 0.60 17.5 26.8 507.5 • 2006 July 31 0.57 17.5 26.7 534.2 • 2006 Aug-Sept 61 0.00 0.0 0.0 534.2 • 2006 October 31 0.40 14.0 7.5 541.7 • 2006 Nov 30 0.55 17.0 22.1 563.8 • 2006 Dec 22 0.60 18.0 20.0 583.8 • 2007 January 25 0.60 19.0 24.0 607.8 • 2007 February 28 0.60 19.5 27.9 635.7 • 2007 March 31 0.60 20.0 31.7 667.5 • 2007 April 30 0.65 20.0 33.7 701.2 • 2007 May 31 0.65 20.0 34.8 736.0

  9. PEP-II Delivered Luminosity (Cont) • 2008 June 30 0.70 22.0 39.9 1091.4 • 2008 July 31 0.65 22.0 38.3 1129.7 • 2008 Aug-Sept 61 0.00 0.0 0.0 1129.7 • 2008 October 31 0.40 15.0 8.0 1137.7 • 2008 Nov 30 0.60 22.0 28.8 1166.5 • 2008 Dec 22 0.65 22.0 27.2 1193.7 • 2009 January 25 0.65 22.0 30.9 1224.6 • 2009 February 28 0.70 22.0 37.3 1261.8 • 2009 March 31 0.70 22.0 41.2 1303.1 • 2009 April 30 0.70 22.0 39.9 1343.0 • 2009 May 31 0.70 22.0 41.2 1384.2 • 2009 June 30 0.70 22.0 39.9 1424.1 • 2009 July 31 0.65 22.0 38.3 1462.4 • 2009 Aug-Sept 61 0.00 0.0 0.0 1462.4 • 2009 October 31 0.40 15.0 8.0 1470.5 • 2009 Nov 30 0.60 22.0 28.8 1499.3 • 2009 Dec 22 0.65 22.0 27.2 1526.4

  10. PEP-II Delivered Luminosity (Cont) • 2010 January 25 0.65 22.0 30.9 1557.3 • 2010 Februar 28 0.70 22.0 37.3 1594.6 • 2010 March 31 0.70 22.0 41.2 1635.8 • 2010 April 30 0.70 22.0 39.9 1675.7 • 2010 May 31 0.70 22.0 41.2 1717.0 • 2010 June 30 0.70 22.0 39.9 1756.9 • 2010 July 31 0.65 22.0 38.3 1795.2 • 2010 Aug-Sep 61 0.00 0.0 0.0 1795.2 • 2010 October 31 0.40 15.0 8.0 1803.2 • 2010 Nov 30 0.60 22.0 28.8 1832.0 • 2010 Dec 22 0.65 22.0 27.2 1859.2

  11. Over all PEP-II Down Schedule 2004-2010 • 2004 down: August 1 to October 15 for BaBar IFR. • 2005 down: July 1 to December 31 for BaBar IFR and PEP-II support tube. • 2006 down: August-September. • 2007 down: August-September. • 2008 down: August-September. • 2009 down: August-September. • Every downtime is planned in great detail (See available handouts).

  12. Accelerator Breakout Plan • "Operations" planning and downtimes J. Seeman • Accelerator operations and efficiency R. Erickson • Safety over-site for operations M. Saleski • PEP-II operations and MDs U. Wienands • Linac beams to other programs R. Erickson • AIP projects J. Seeman • PEP-II RF operations and upgrades R. Larsen • PEP-II IR upgrades M. Sullivan