ISPA Measure 2002 BG 16 P PE 015 WWTP Popovo and main collectors. Works Contract. Commencement Date: 13 th June 2007 Completion Date: 31 st Dec. 2009 Physical Execution: 100 % Financial Execution: 100 % WWTP became operational on 29 th March 2010
E N D
ISPA Measure 2002 BG 16 P PE 015 WWTP Popovo and main collectors
Works Contract • Commencement Date: 13th June 2007 • Completion Date: 31st Dec. 2009 • Physical Execution: 100 % • Financial Execution: 100 % • WWTP became operational on 29th March 2010 • 1 year DNP will expire on 29th March 2011
Supervision Contract • Commencement Date: 24th April 2007 • Completion Date: 30th April 2011 • Time elapsed: 100 % • Financial Execution: 100 %
Compliance with Article 8of the Financing Memorandum Art. 8.3.a) According to EC’s letter Ref. REGIO I2/UN/ sd (2011) 910308 dated 01.08.2011 the conditions under point 8.3.a are considered as fulfilled. Art. 8.3.b) According to EC’s letter Ref. Reg12/SP/vg D/(2010)920241), 007401 dated 16.08.2010 the conditions under point 8.3.b are considered as fulfilled. Art. 8.3.c) According to EC’s letter Ref. Reg12/VN/vg D/(2011)668482), 610178 dated 07.06.2011, the EC considers the conditions under Article 8.3.c as fulfilled.