190 likes | 314 Views
LED PROJECT PROGRESS. IDPRF 9 APRIL 2010 . AMAJUBA TECHNO PARK (R1,2 Billion) 1600 Jobs. EIA in progress Negotiations with China . HORN RIVER DAIRY PROJECT (R75 Million). Delayed implementation Negotiations currently underway with China. HERBS AND MEDICINAL PLANTS (R 10 Million).
E N D
LED PROJECT PROGRESS IDPRF 9 APRIL 2010
AMAJUBA TECHNO PARK(R1,2 Billion) 1600 Jobs • EIA in progress • Negotiations with China
HORN RIVER DAIRY PROJECT (R75 Million) • Delayed implementation • Negotiations currently underway with China
HERBS AND MEDICINAL PLANTS(R 10 Million) • Feasibility & Business Plan Revision • Awaiting trial results
AMAJUBA TANNERY (R50 Million) • Site has been obtained in Dannhauser for the establishment of the Tannery • ADM currently appointing consultants for the EIA • Application for training has been submitted to DED • Est. Job Creation 35 Permanent
AMAJUBA MEAT DEBONING PLANT (R 40 million) • Equity Partner Negotiations • Project will include feedlot through Partnership • Currently negotiating with financiers • Est. Job Creation – 65 Permanent
REGIONAL SOYA/MAIZE PROJECT • 2000 Ha of soya has been planted and funded by Staplotrade PTY Ltd • Soya is currently being harvested
REGIONAL MARKET/LOGISTICS HUB • Consultants appointed to conduct feasibility study and business plan
ADM KENAF, SOYA, MAIZE, BEANS & POTATO TRIALS • Soya results are fair • Maize results are good • Dry beans are fair • Potatoes are fair • Kenaf was not planted
MECHANIZATION(R 17 Million) 5000Ha • Equipment purchased for planting maize and soya • Currently finalising additional equipment for vegtable production
AQUACULTURE & AQUAPONICS • Primary production of fish has commenced • Tunnels currently being established on site
ORCHARD • Implemented • Irrigation layout pending • Will include olives, lemons, oranges, pomegranate & peaches
JEWELRY PROJECT • Complete, mentoring and advise
MUSHROOM PROJECT • Site has been identified • Currently identifying a mentor for the implementation of the project
LED & WATER SYNERGIESIRRIGATION • Feasibility study & BP complete • Irrigation license for 1200Ha pending project implementation • Currently implementing 25 Ha of irrigation
POVERTY ALLEVIATION • ADM has developed a policy and monitoring & evaluation tools for projects • ADM has established a committee • Project implementation is being co-ordinated by the committee
LED SKILLS DEVELOPMENT • 5 year skills development plan has been submitted to the Dept of Labour • Currently waiting for the outcome of the submission
ICT • ADM established an ICT forum to drive the establishment of an incubator. • Feasibility study completed by DED which indicates that we may proceed with the project. • The next step is the preparation of a Business Plan.