1 / 27

SMACC Fifth report [20 min ] 28/06/2013

Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project. SMACC Fifth report [20 min ] 28/06/2013. Activities since last LSC (14/06/2013) Status of SMACC-QA (R Ostojic’s presentation) Activities for the next 2 weeks Considerations on progress and planning Conclusions.

Download Presentation

SMACC Fifth report [20 min ] 28/06/2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project SMACC Fifth report[20 min ]28/06/2013

  2. Activities since last LSC (14/06/2013)Status of SMACC-QA (R Ostojic’s presentation) • Activities for the next 2 weeks • Considerations on progress and planning • Conclusions

  3. SMACC Main activities for the next 2 weeks • Sector 56 : • Continuation of on-going activities (Arcs and DFBAs with restart of broaching) • Restart welding at a substantial speed • Complete electrical measurements on the quadrupole diodes • Sector 67 • Complete the opening of the M-lines • Complete the opening of the quadrupole diode containers & startelectricalmeasurements • PerformElQC on presentsplices • Sector 78 • Continue installation of DN200 • Start opening of IC (> 50 % have already W-bellowsopened to allow DN200 installation) • Sector 12 • Disconnect cryodipoles to be replaced (Rate : 1-2 per week)(Objective: All 18 cryomagnets disconnected for end of August 2013) • Other sectors: • Special interventions/investigations From last LSC (14.06.2013)   Welding restarted in 56, see next slide Was presented last LSC by L Grand-Clement  Also started in 81 for advanced info on existing splices    Opening of diode containers also in 78  > 70% (#123) are installed  142 ICs are completely opened + 50 W bellows opened  All (#6) are disconnected, starting in S23 (#2) 

  4. SMACC Progress report Activities since last LSC • Opened interconnections in 8 sectors, almostequivalent to 4 sectors Some team members will reinforce ELQC and DN200 activities

  5. SMACC Progress report Activities since last LSC • ELQC measurements • See R Ostojic’s presentation • Critical NC LHC-QN-QBBI.A21L6-M2-Int-cable • Investigations are on-going (not top priority) •  Less critical outlier in S45: Magnetistaion results shows that there is no significant Ic degradation. (Detailed report at a further LSC) • Conservative measure: • Investigate other outliers (Open IC, open M, (enhanced) ELQC but NO splices desoldering [Limited spare availability] (Not top priority)

  6. SMACC Progress report Activities since last LSC • Quadrupole diodes • S56 & 67 opened, 23/51 opened S78 • One component (Inconel threaded piece) is expected to be delivered next week [Delay for starting the actual consolidation, progress on opening diodes containers] • NC corrected, validated by electrical tests Courtesy L Grand-Clement

  7. SMACC Progress report Activities since last LSC • M insulation installation • 68 ICs equipped (See issue with interference with M lines) [Was 52 2 weeks ago] • ELQC procedure updated • SeeRanko’spresentation • M-welding • 18 ICs released beginning of the week. (6 where only M3 has to be welded): Now 4 remains / 10 were welded this week, not yet controlled • 10 more couldpotentiallybereleased if accepted to come back for diode containers rewelding and the equivalent of 7 more ICscouldbereleased if individualslines are welded: Not the optimum use of weldingresources but betterthan not working

  8. SMACC Progress report Activities since last LSC • DFBA Consolidation • Broaching incident reproduced in workshop conditions LSC 31.05.2013 In workshop, at 318 bars (Now pressure limited at 150 bars) • Damaged splices have been desoldered and are under resoldering • Broaching to restart next week; on the critical path for DFBA consolidation, not (yet) for SMACC Courtesy R Principe

  9. SMACC Progress report Activities since last LSC • DFBA Consolidation : RCS.A56B2 (DFBAK and 11 otherones) • MP3 recommendation presented by M Modena at last LSC • Proposalwaspresented and approved by MP3 thisweek Perimetral glass-epoxy foil protection (0.5 mm thickn.) PEEK protection (optional, 2 halves) PEEK protection (2 halves) Spacer to avoid overheating (concept) - function: protection againts wear and insulation if damage - smooth insulating surfaces - minimal thickness to avoid deforming the busbars (≤ 2 mm) - strong and very resistant to wear - avoid overheating (being validated) Courtesy A Perin

  10. SMACC Progress report : Dashboards Forecast 4 LSCs ago Concern : Busbar position and consequent interference between M lines and insulation box Nevertheless, 193 ICs are now equipped with shunts (> 90% of a sector) Welds not yet entered because not controlled

  11. SMACC Progress report : Dashboards Start shunt installation in sector 67. Is it good news?

  12. SMACC Some dashboards Working on a simplified view

  13. SMACC Some considerations on progress and planning Progress: Baseline: 4.4 % Achieved: 8.4 % Advance: 15 days

  14. SMACC Some dashboards

  15. SMACC Some considerations on progress and planning Progress: Baseline: 14.6 % Achieved: 11.4 % Delay 10 days

  16. SMACC Some considerations on progress and planning Progress: Baseline: 12.3 % Achieved: 6.6 % Delay 29 days

  17. SMACC Some considerations on progress and planning Progress: Baseline: 54 % Achieved: 20 % Delay 42 days

  18. SMACC Some considerations on progress and planning Progress: Baseline: 8.4 % Achieved: 8.9 % Advance: 1.5 days

  19. SMACC Some considerations on progress and planning • First sign of the «last 10-20% effect» • Non-conformities are leftbehind to keep good train progress • SIT shouldbecome free later to solvethese issues • In first sectors, marginwrt pressure test, Coactivity ! Not in the last ones ! • One local NC blocks 1 subsector(214 m / 16 ICs)

  20. SMACC Some considerations on progress and planning • Main 13 kA Splices: •  Started a week in advance, now 2 weeks • Special Interventions: •  10 days delay: late release of some sectors (45) • DFBA: •  1 month delay: Issue with broaching procedure • DN200: •  > 1 month delay: late release of sector 78 / Start up difficulties • SMACC: •  1.5 days advance (but we started one week in advance) • Only completed activities are accounted for, not the on-going ones • Weighting factors are based on initial estimates • Achieving baseline rates per activity has to be demonstratedSequential processFocus on quality first, then production rates • Mindthe last 10 % effect (Minimum consequence on first sectors)

  21. SMACC Main activities for the next 2 weeks • Sector 56 : • Continuation of on-going activities (Arcs and DFBAs with restart of broaching) • Continue welding of M lines at an increased rate • Investigate the overheated cable (21L6) • Sector 67 • Continuation of on-going activities (Arcs and DFBAs with restart of broaching) • PerformElQC on presentsplices • Sector 78 • (Almost) complete installation of DN200 • Complete opening of IC • Reconnect the disconnectedcryodipoles (#2) • Sector 81 • Open M lines and perform advanced ELQC on about 20 ICs • Sector 23, (34 or 45 depending on access constraints) • Disconnect cryodipoles to be replaced (Rate : 1-2 per week)(Objective: All 18 cryomagnets disconnected for end of August 2013) • Other sectors: • Special interventions/investigations

  22. Conclusions • Strategy under implementation for the higher number of splices to redo (Teams reinforced) • Solution ready for DFBA splicesbroaching • Main concerns : • Interference between insulation box and M lines caused by non-nominal busbars position and impact on welding activities • Overheated cables and high R@ 1.9K investigation to define repair procedureCould require replacement of a magnet • Still within schedule, margin decreased • Focus on qualitythen production rates • Long way to go … on good trackswith a motivated team

  23. 25.06.2013 : Completion of the M lines opening in the second sector (S67) Courtesy JM Hubert / A Aijaz

  24. 24.06.2013 : Thermal shields preparation in 183 : OK for 2 sectors Courtesy G Barlow

More Related