Accelerator and NuMI Upgrades Shutdown Update

Accelerator and NuMI Upgrades Shutdown Update. Cons Gattuso June 3, 2013. NuMI Activities. Horn 1 and Horn 2 Installation is complete Pulse testing scheduled for next week Target Has been installed in the chase Preparing for power supply testing (next week) Interlock testing

Download Presentation

Accelerator and NuMI Upgrades Shutdown Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Accelerator and NuMI UpgradesShutdown Update Cons Gattuso June 3, 2013 Cons Gattuso

  2. NuMI Activities • Horn 1 and Horn 2 • Installation is complete • Pulse testing scheduled for next week • Target • Has been installed in the chase • Preparing for power supply testing (next week) • Interlock testing • Pretarget down to target hall • Prepare chase for Horn pulse testing & thermal scan of stripline • Next week, process will take ~3 days • General • Raw water systems • Complete and running: Target, Horn 1, Horn 2, All RAW skids system, exchange systems tested and operations • Completed beamline vacuum work & all ion pumps on. Final survey completed. • Started demobilizing shutdown equipment from Target Hall • Closed up By the 14 of June…. • Installed LBNE Muon Monitor prototype infrastructure in Absorber Passageway

  3. NuMI Target Hall

  4. NuMIBeamline

  5. MI/RR Shutdown 2012 • Injection Line Remaining Work: • Magnet installation • Complete • Vacuum system • MI • 100% Complete and under vacuum • Recycler • Q848-100 installed • Leak checked fine • Q100-Q104 • Beam Box installation on new stand complete • Cable termination 100-105 • Powered elements • Cable terminations -95% complete • Instrumentation • Cable terminations -95% complete • Alignment • MI and RR from 848-102 complete • RR from 102 to 105 still left to be done • Installation of components and vacuum system

  6. MI/RR Shutdown 2013

  7. MI/RR Shutdown 2012 RR-30 straight: • MI primary collimator marble shielding re-installation is complete • Bake is completed downstream of 309. • Bake is completed upstream of 229. • Installing Recycler Ring beam pipe between girders: Approximately 90% complete. • 229 Recycler Kicker spool installed, kickers pumping down. • Replacing corroded MI beam pipe (301-304) • Starting on MI re-assembly at 306 – 308 • Need MI drawings • Reworking multiwire installations to • clear obstructions

  8. MI/RR Shutdown 2012 Still addressing MI corrosion issues in 30 straight section

  9. MI/RR Shutdown 2012

  10. MI/RR Shutdown 2012 MI 52 Lambertson: Leak checks complete Bake terminated today Blankets off tomorrow followed by the leak check.

  11. MI/RR Shutdown 2012 RR 53 MHz Cavity Installation

  12. MI/RR Shutdown 2012 • RR Bakes: • Bake status ~97% complete • 105-109 Completed 601-607Completed • 125-203 Completed 608-610Completed • 210-219 Completed 620-627Completed • 319-328 Completed 227-229Completed • 335-400 Completed309-311 Completed • 618-620 Completed MI306 Lambertson ( extraction line) • Bake what were added during the shut down • 219-227 Completed, was added due to a component failure • 527 -601 Completed, was added due to MI buss repair • MI521-522 Completed, MI 52 lambertson Flange leak

  13. Shutdown Dose Accumulation Cons Gattuso

  14. MI Radiation Shielding Status • Sight Risers • One of three fabricated • Service Building • LCW – 100 % complete • Power Supply Cabinets 100 % complete • MI-60 • RF Penetrations • Empty RF Penetrations 100 % complete • Rooms 117 &118 Cons Gattuso

  15. Radiation Shielding • Service building power supply/LCW headers 100% complete * • MI-60 • Empty RF penetration 100% complete * • RF Penetrations – installation underway • Sight Risers * • Welding and installing by the end of first week of June • 1 of 3 is welded up and ready for installation • Problem areas • MI60 LCW Penetrations • Waiting on material • Steel to arrive mid June • Poly to arrive late June ( installation ~ 1-2 days) • Power supply Rooms 117 and 118 ( completion aprox. first week of July) • Waiting on designs (poly block) • Est First week of June • Waiting on ploy block • Est first week of July * (required to run low intensity beam) Cons Gattuso

  16. Shielding Types Sight Riser Buss penetrations Room 118 LCW penetrations RF penetrations Room 117 Cons Gattuso

  17. Recycler Shims • Fabrication has started on the RGD shims • Completed sometime middle/late of June • Fabrication of the RGF Shims • Start late June/early July • Completed by the middle July • Tunnel installation could start mid June • Conservative est. Would have them complete installed sometime Mid-End July (WAG) Cons Gattuso

  18. MI/RR Shutdown 2012 Startup activities for last week: • Removed all locks from the MI/RR MCR LOTO box by Friday. • Re-core tunnel to standard tunnel access keys for the weekend. • Safety system tests were successfully completed • Successfully high potted all the MI busses to 1 KV • To many faults were removed to list… • Re-core back to shutdown keys on Monday morning to continue with tunnel installation Startup activities for this week: • Removed all locks from the MI/RR MCR LOTO box by Friday. • Re-core tunnel to standard tunnel access keys for the weekend. • Main Buss Power supply testing through out the weekend • Re-core back to shutdown keys on Monday morning to continue with tunnel installation

  19. Cons Gattuso