An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PIP UpdateLinac Utilities for 2014 Shutdown Matthew Gardner, 8/20/14

  2. Dual Temp Water System • Replace old water based AC system with conventional rooftop AC system. Drain and abandon old water lines. • Remove old air handlers and sections of pipes that conflict with new ductwork. • Pipe insulation contains asbestos, abatement will take place August 29th. • Relocate a VESDA conduit. • Bid package was delayed by procurement. Sent out on August 18th. Bid due date is August 29th. • Ductwork installation should begin in the 2nd or 3rd week of September. Expected to take ~4 weeks. • The Rooftop units have a lead time of 6-8 weeks. • This may not arrive before the shutdown ends.

  3. CUB Chiller#3 Spare Pump • Concrete pad waiting on chiller overhaul. • Expected to happen next week. 1-2 days. • Electrical Work will begin next week. • Expected to take ~2 weeks. • Pipe Fitting • All of the prep work that could be done before cutting into existing system is complete. • Was waiting on chiller overhaul before continuing. • Rising costs prompted switch from T&M to fixed price. • Package has been sent out for review and will go out to bid this week or next. • Remaining work is expected to take 3 weeks.

  4. L1 Substation Replacement • Transformer was moved to Linac Lower Gallery on July 19th. • Transfer temporary power to L2 on September 6th. • 2 weeks to remove old substation and install new one. • EE Support, Electricians, and Riggers • Switch power to new substation on September 20th.