Maintenance and Accelerator Support. RHIC run10. Results May 19 th :. A long day, well executed 100+ individual jobs executed Work Scheduling and planning was successful, both prior and during the day. Excellent work, especially Vacuum and Instrumentation Groups.
E N D
Maintenance and Accelerator Support RHIC run10
Results May 19th: • A long day, well executed • 100+ individual jobs executed • Work Scheduling and planning was successful, both prior and during the day. • Excellent work, especially Vacuum and Instrumentation Groups. • Physics restored by 9pm-not bad. • I limit key is in the control room!
Thursday: • No Injector Access • Tandem down for 3 hours to change foil holder position • RHIC RCA access for: • PHENIX (ring and tunnel) • RHIC PSG (8Z2, 9Z1) • Sectors 5-9 for HP survey • NSRL running protons all day • Some “transparent” ACS work at Booster- back out plan of problems
Draft Schedule: • 0800: • 7.7GeV run ends • Begin RCA Access to IRs • HP surveys, RAC 3 groups • 0900: • Access 9Z1 for inspection with HP on RCA • 1000: Begin setup for 11.5 GeV running