Maintenance and Accelerator Support

Maintenance and Accelerator Support. RHIC Run 12. Last weeks maintenance:. Morning stymied by Power Dip: DX training was delayed. Early RHIC Ring Tunnel Access for polarimeter delayed. Scheduled Maintenance Items completed very well. R HIC polarimeter work.

minor
Download Presentation

Maintenance and Accelerator Support

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Maintenance and Accelerator Support RHIC Run 12

  2. Last weeks maintenance: • Morning stymied by Power Dip: • DX training was delayed. • Early RHIC Ring Tunnel Access for polarimeter delayed. • Scheduled Maintenance Items completed very well.

  3. RHIC polarimeter work • Both Yellow and Blue targets replaced. • Noise reduction modifications completed. • Excellent work and support from Vacuum, Instrumentation, Polarimeter and other groups. • Pump down time utilized by PHENIX and to compete DX training

  4. General: • RHIC tunnel opened 0900-1700hrs for maintenance. • ~90 jobs 250 man/hours. • Vacuum access between DX trainings in the evening until 2100hrs.

  5. Next Maintenance: • Requests being reviewed. • Early submission as much as possible. • Discussion Thursday at Supervisors meeting. • Final plan following next Tuesdays Scheduling Meeting Here at 1430hrs…