1 / 7

Accelerator Support and Maintenance

Accelerator Support and Maintenance. Run 14. Machine Status: Injectors. LINAC: On For BLIP: Maintenance next Monday Independent from RHIC this year. Booster and AGS running setup with beam. Possible late week access for any issues, next maintenance day would be just before Physics.

ellie
Download Presentation

Accelerator Support and Maintenance

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Accelerator Supportand Maintenance Run 14

  2. Machine Status: Injectors • LINAC: On For BLIP: • Maintenance next Monday • Independent from RHIC this year. • Booster and AGS running setup with beam. • Possible late week access for any issues, next maintenance day would be just before Physics.

  3. RHIC Activity and start up. • Adjacent areas are being secured (Berms and roof tops). • Rad and other postings at RHIC start this week. • All tunnels areas of RHIC will remain on RA through Friday, except for the 4 o’clock IR.

  4. Installation updates • 56MHz installation nearing completion: • Walk way and shield wall installation possible Thursday. • AC dipole: • Vacuum chamber being prepped for bakeout(horizontal only). • Re-assembly Saturday and completion on Maintenance Days.

  5. Installations continued: • Stochastic Cooling: • Kickers are installed at 4 and 11 o’clock. • Bakeout at 11 to be complete mid week. • Re-installation is ongoing and will be completed on MDs. • Transverse damper: • Bake out nearing completion. • Re-installation also MDs.

  6. Testing in RHIC • ACS tests and RF conditioning testing 8pm to 7am Wednesday. • Ramping Friday and Saturday nights possible (tunnel access prohibited except STAR and PHENIX). • eLens work possible late in the week or weekend.