REGIONAL CONFERENCE ON EHNANCING INTEGRITY IN PUBLIC PROCUREMENT. Presentation By Egal N. Roble (Chief Officer, Procurement Reform) REGIONAL CONFERENCE ON EHNANCING INTEGRITY IN PUBLIC PROCUREMENT Venue: Rabat, MOROCCO Date: APRIL 3-4, 2008. Content. Introduction/Context
E N D
REGIONAL CONFERENCE ON EHNANCING INTEGRITY IN PUBLIC PROCUREMENT Presentation By Egal N. Roble (Chief Officer, Procurement Reform) REGIONAL CONFERENCE ON EHNANCING INTEGRITY IN PUBLIC PROCUREMENT Venue: Rabat, MOROCCO Date: APRIL 3-4, 2008
Content • Introduction/Context • Role of Borrower • Role of Bank • Before Award • During Award • After Award • Anti-Corruption Strategy • Redress Mechanism • Integrity Measures
Financed Operation Translates to: Works Goods Services Through Lending Instruments • Project Loans • Lines of Credit • Investment Loans • Structural Adjustment Loans • Technical Assistance Grants
MOROCCO: Example 2 • Total Amount approved in: • 2003: UA 179 million • 2004: UA 257 million • 2005: UA 114 million • 2006: UA 172 million • 2007: UA 174 million • Cumulative amount approved over the last 5 years: UA 896 million
Context • Pursuit of Economy and Efficiency • Ensuring Equal Opportunity for all Eligible Bidders • Encouragement of the Development and Participation of Regional Firms • Transparency and Integrity in theProcurement Process
Role of the Borrower • Preparation of Bidding Documents and • Prequalification Documents • Prequalification Process • Bid Evaluation
Role of the Borrower • Advertises and Issues Bidding Documents; • Evaluates and Selects; • Awards, Signs and Administers Contract; • Supervises Contract Execution • Processes Invoices for Payment Bank required to approve or commenton each stage of the selection process PPRU/Procurement Unit
Role of the Borrower • Negotiation, Award and Signing of Contracts • Contract performance • Consideration of Claims • Settlement of Invoices
Role of the Bank • The Bank is not Party to the Contract • Preparation of Bidding Documents: Mandatory Use of Standard Bank Documents, • Free Access to UNDB • Bank’s “No objection” for Bidding Documents
Role of the Bank • Procurement Process Verified at Each Stage • Bank’s “No objection” for Bid Evaluation Report Prior to the Award of Contracts • Imposition of Sanctions relating toFraud and Corruption
Issuesin Procurement Planning • 3. Types of Financing: • Parallel Financing or Joint Financing • Who is Procuring What? • 2. Sources of Financing: • Government or Local Administration; • Bilateral Funding Agency; • Multilateral Funding Agency; • Several Sources of Funding. • 4. Procurement Rules to be Followed: • Local Procedures; • Procedures of Bilateral Sources; • Procedures of Multilateral Sources; • Procedures of the Major Financier; • A Combination of Procedures.
Before Award: Sources of Information on Bank Group-financed Projects • Press Releases • Appraisal Reports • Quarterly Operational Summary (QOS) of Projects • United Nations Development Business • Bank's Web site: www.afdb.org • ADB Business Bulletin • Project Executing Agencies in Borrowing Countries
Registration- DACON A new on-line registration system is now available at the following address: http://ext.afdb.org:8080/ADBDaconWeb/dacon/Home.htm
Before Award • List of procurement items to be acquired under the project: Goods (equipment, vehicles, supplies, fertilizers, books), Works to be constructed or rehabilitated; and Consultancy Services (technical assistance, advisory, training, supervision) to be acquired. • Determine (APA) target dates (inter-relationships) within the overall project implementation framework. • Decide on the content of procurement packages;
Before Award: Bid Packaging • Time Element: items are needed at different times; • Management Aspects: one main contractor or EA; • Competitive Aspects (how to divide items into lots of optimum size to encourage maximum competition); • Business Structure (goods or services are not available from a single source); • Administrative Costs of Tendering; • Point of View of Co-financing.
Before Award:Consultancy Services – Short-listing Composition: Qualified Firms or Consortia • Requirements: • 5 to 7 firms; • Wide geographic distribution (not more than two firms from same country); • At least one firm from a regional member country; and • Consortium/joint venture of firms from member countries encouraged
During Award International Competitive Bidding • Advertisements: Publication of GPN in UNDB Publication of SPN in UNDB • Mandatory use of Standard Bidding Documents • Bidding Documents to contain all contract conditions • Minimum Bid Period - 60 days • Clarifications on Bidding Documents
During Award International Competitive Bidding • Public Opening of Bids • Evaluation Criteria Specified in Bidding Documents • Evaluation undertaken based on these stated criteria • Contract is awarded to Bidder with the "LOWEST EVALUATED COST BID"
During Award:Evaluation of Consultants’ Proposals 3 Selection Procedures 1. Selection based on technical quality; 2. Selection based on technical quality with price consideration; 3. Selection based on establishing the comparability between technical proposals and selection of the lowest offer
Placing the Contract • Bank reviews contract • All main conditions examined • No Objection needed • If obtained,contract may proceed
After Award: Contract Management • Vitally important • The Borrower is responsible.
After Award: Contract Supervision • Reporting • Means by which the contract is controlled • Must include: • Progress of work • staff months spent • Money spent
After Award: Disbursement • Borrower responsible to settle payments • Payments upon Borrower’s request: • Direct to beneficiary; or • Letter of Credit; or • Revolving Fund (Borrowers Pay) Disbursement (payments) in contract currency The Bank’s policy on arrears and Sanctions
After Award: Contract completion-closeout • Draft final reports to be reviewed and approved • Accounts closed • Demobilisation of consultants staff • Evaluation of consultants staff
MOST COMMON CORRUPT PRACTICES • BID MANIPULATION/COLLUSION • BRIBERY • KICKBACKS • MISREPRESENTATION
Anti Corruption Strategy • Bank’s policy: Borrowers and beneficiaries as well as bidders/ suppliers/ contractors/ consultants must observe highest standard of ethics during the procurement and execution of contracts under Bank financed projects, programs and studies. • Bank’s policy: Borrowers to include standard provisions against corrupt and fraudulent practices. • Standard Procurement Documentation of the Bank includes detailed Clauses on the matter.
Anti Corruption Strategy • Following its own investigation and determination in accordance with its procedures, the Bank will: • Reject a proposal for award if it is determined that the bidder recommended has engaged in corrupt or fraudulent practices in competing for the contract; • Cancel the portion of the loan or grant to contract if at any time it is determined that corrupt or fraudulent practices were engaged in by the Borrower or representatives; • Declare a firm ineligible, either indefinitely or for a stated period of time , to be awarded a Bank financed contract if it at any time determines that the firm has engaged in corrupt or fraudulent practices in executing a Bank financed contract.
Anti Corruption Strategy • Where a firm has been found by a national or international entity to have engaged in corrupt or fraudulent practice, the Bank reserves the right to declare such a firm ineligible to be awarded a Bank financed contract. • The Bank reserves the right to require that a provision be included requiring suppliers and contractors to permit the Bank to inspect their accounts and records.
Misprocurement • Bank Does not finance Expenditure Not in line with Loan Agreement and Bank Rules • Banks’ Policy to Cancel the Misprocured portion of the operation • Bank will Cancel the Entire Loan if the Misprocured Portion is major • Bank will Declare Misprocurement if contract Award was Based on Incomplete, Inaccurate or Misleading Information
Redress Mechanisms Procurement Review Committee (PRC) • Neutral and Independent • Reviews receivable complaints • Makes final decision on behalf of the Bank
PRCOUREMENTINTEGRITY: MEASURES • Capacity building • CPARs • Party to all conventions: MDBs • Strict Prevention and Punishment tools • Transparency emphasised in all phases/Strict Review for Redress • Institutional Integrity Division built in the OAGL • Management – in all levels - Committed • Staff/Board Code of Conduct
ADDITIONAL MEASURES • Voluntary Disclosure Program • Detailed Implementation Review • Tighter Procedures for National Competitive bidding • Rationalization of BEC Membership • Information Sharing and Cross Debarement • Protection of Whistleblowers • Stricter Guidelines on Anti-Corruption and Sanctions