ICT 2009 Reliability Assessment and Construction Plan Evaluation. Entergy Transmission Summit August 11, 2009 Astor Crown Plaza New Orleans, Louisiana. Overview. Background Scope Draft Construction Plan Results. Background.
E N D
ICT 2009 Reliability Assessment and Construction Plan Evaluation Entergy Transmission SummitAugust 11, 2009Astor Crown PlazaNew Orleans, Louisiana
Overview • Background • Scope • Draft Construction Plan • Results
Background • Reliability Assessment is performed pursuant to Entergy’s Open Access Transmission Tariff (OATT) Attachment K. • Objectives: • Assess of the ability of the Entergy transmission system to perform according to the Planning Criteria. • Evaluate the Construction Plan’s ability to mitigate any performance deficiencies found. • Provide basis for development of the Base Plan.
Background • Draft report was made available for stakeholder review and comment • Posted on Entergy’s OASIS July 17, 2009 • Presentation made at LTTIWG July 22, 2009 • Final report is posted on Entergy’s OASIS. • Detailed information not included in report is posted • Background models, data, and other information is posted
Entergy Planning Criteria • Planning Criteria • NERC Planning Standards • SERC Supplements • Entergy’s Local Planning Criteria • Entergy’s Business Practices (Planning Guidelines) • Posted on Entergy’s OASIS • NERC Planning Standards being revised
Reliability Assessment Scope • Models • Near-Term Period: Summer & Winter 2010 & 2014 • Longer-Term Period: Summer 2018 • Construction Plan Projects • Initial Scan: Approved Projects from 2009-11 Construction Plan • CP Eval: Approved and Proposed Projects <2010-12 Construction Plan • System Intact Review – Category A • Contingency Scan – Category B • Sensitivities • Specific Load Pocket Criteria • Low Hydro Sensitivity
Entergy’s Draft Construction Plan 2010-2012 • May 13, 2009: Original Draft Posted • July 16, 2009: Revision 1 Posted • August 3, 2009: Revision 2 Posted • 25 New Projects • 10 Accelerated Projects • 4 Delayed Projects • 20 Projects reported in the 2008 Differences Report • 12 were directly included in the draft CP project • 7 were replaced in the draft CP by an alternative project • 1 was partly included; the full project is expected in a later CP
Map Legend Contingency Scan Results with Entergy’s Draft Construction Plan Projects Included Key to Map Highlights Annotations Overloads and Low Voltages Planned Upgrade from Entergy’s Draft Construction Plan Year Color Key Other Notes Solution being investigated
Grandview-Osage Creek 161 kV Line Melbourne-Sage Line Upgrade Harrison East Upgrade
Holland Bottoms-Hamlet New 161 kV Line Holland Bottoms New Station Lynch-McAlmont 161 kV Overload
Benton North-Benton South 115 kV Line Hot Springs-Bismarck-Alpine-Amity Upgrade
Horn Lake 230/161/115 Freeport 500/230 Greenbrook 115 Twinkletown 230 Plum Point 115 165 MW Nesbit 115 Church Rd 230 Getwell 230/115 Hernando 115 Batesville 230/115
Kenner-Snakefarm SE Louisiana Coastal Improvement
Sabine-Port NechesPort Neches-Linde Kolbs-Lakeview
Low Hydro • Simulate reduced availability of hydro units during summer peak • Conway (Arkansas) Area • Harrison-Eureka 161 kV • Norfork-Sage 161 kV
Load Pocket Criteria • Application of Specific Load Pocket Criteria • Western • Amite South • Downstream of Gypsy (DSG) • G-1, N-1 • No new problems identified.
Base Plan Development Next Steps • Today-August 31: Stakeholder Input/Comments on Projects for Base Plan and Construction Plan • Stakeholder comments will be posted on Public OASIS (per Attach. K) • September LTTIWG: Present/Discuss Comments • October/November LTTIWG: ICT presents draft Base Plan for comment • Year End: Final ICT Base Plan Posted; Final Entergy Construction Plan Posted
Steve PurdyLead Engineer, ICT Planning501-614-3371spurdy@spp.org Questions?