1 / 17

Project Closeout

Project Closeout. (This is mostly additional information. Also refer to Chapter 8 of the textbook.). Overview. The last major phase of a project’s life cycle is the project closeout phase.

dardar
Download Presentation

Project Closeout

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Closeout (This is mostly additional information. Also refer to Chapter 8 of the textbook.)

  2. Overview • The last major phase of a project’s life cycle is the project closeout phase. • Project closeout is performed after all defined project objectives have been met and the customer has formally accepted the project’s deliverables and end product. • Project closeout is fairly routine, but it is an important process. • By properly completing the project closeout, organizations can benefit from lessons learned and information compiled at closure.

  3. Overview • The final completion/formal payment may be delayed if closeout is not done properly. • The size of the task of closing out a construction project seems to have little correlation to the size of the project. • Getting that last one percent of the job finished and approved can be as agonizing for a $10,000 project as it is for a $10 million project. • Part of the reason for this dilemma is that there is a vast difference between having the project substantially complete and having it finally complete.

  4. Overview • A successful construction project can be adversely affected by improper closeout procedures. • All contract work must be satisfactorily completed, outstanding claims resolved, change orders fully negotiated and processed, extension of time reports approved, operations and maintenance manuals approved, as-built drawings completed, and all other contract goals achieved. • In addition, all certifications and warranties must be in place. • A proper project closeout must also conform to the client's established procedures.

  5. Complete vs. completed • Substantially complete implies that the project is ready for use by the owner. • The owner may use or occupy the project; the warranties go into effect and the owner assumes responsibility for the operation and maintenance of the project. • Substantial does not mean final. • There may still be a lot of punch list items to complete; • the contractor may have a number of submittals to make to the owner; and • final inspections and paperwork need to be completed before we reach the stage of final completion. • It is awfully easy for those last tasks to take on a lower priority when the pressure is off to get the owner a useable project.

  6. Complete vs. completed • Closing out a project is a real team effort. • It involves • product manufacturers, • suppliers, • subcontractors, • the prime contractor, • consultants, • the architect-engineer and • the owner. • Most standard General Conditions have very definitive procedures for closing out a project.

  7. Procedures • Contractor inspects project and prepares a list of items not completed. • A/E, contractor and owner inspect the work to verify substantial completion. • A/E prepares tentative certificate of substantial completion with attached tentative list of items not completed. • Owner approves a tentative certificate. • A/E prepares definite certificate of substantial completion with a • revised list of items not completed. • Contractor submits notice of final completion. • A/E inspects project to verify final completion. • A/E processes final application for payment and closeout submittals. • Owner makes final payment.

  8. Procedures • If any on of the team members fails to participate in these closeout procedures, the formal completion of the project will be delayed, and sometimes for months. • Getting out of that limbo between substantial completion and final completion can be hastened by a conscious effort by all team members to see that • the punch list items are completed on a timely basis, and • by having the contractor ready at the completion to make some important submittals to the A/E and owner.

  9. Submittals • Final application for payment • Affidavit of payment of debts and claims • Certificates of insurance extending beyond final completion • Consent of surety to final payment • Releases and waivers of liens • Project record documents • Special warranties • Bonds • Maintenance agreements • As-built drawings • Operation and maintenance manuals

  10. Other Items • The A/E should be ready to prepare a final change order, if necessary, to clean up outstanding items that have not been completed, and to make the final inspection and issuance of the final payment. • Unless stipulated otherwise by the contract, final payment constitutes project completion.

  11. Closeout Conference • An effective way to help assure smooth project closeout is to conduct a closeout conference just before the substantial completion to make sure everyone understands the contractual responsibilities. • These responsibilities may have been discussed at the beginning of a project, but months, or even years, can pass before the project nears completion, and it is a good idea to bring the key parties to the table to review those procedures. • A good set of contract documents will define procedures for project closeout. • If all parties conduct their operations in accordance with the contract, getting that last one percent of the project completed will be a lot easier.

  12. Some Critical Aspects of Closeout • Use checklists — lots of checklists. • When planning the other phases of the project, there is usually some logical sequence to completing the tasks. • Most of this disappears during the final 10 percent. • Your focus should now shift to crossing off items on various checklists until none remain. • Don’t allow anyone to work on any item that is not on the checklist. • This is extremely important. • People will always find something more interesting to do than close out punch-list items. • These distractions waste the budget and do nothing to complete the project. • Insist on frequent meetings, sometimes several times a day, to keep the focus on closeout.

  13. Some Critical Aspects of Closeout • Build your firm’s intellectual capital through “lessons learned.” • At the end of each project, collect the lessons learned by the project team and work them into improving the firm’s processes. • Perform the project completion analysis and document what went well and what did not. • Be a learning organization — don’t repeat past mistakes. • Make every effort to safeguard the project records. • If trying to find the back-up calculation for a certain structure is difficult when the project is in the design phase, it’s impossible five years later! • Leaving all your project records in file cabinets until someone else needs the cabinets is not records management.

  14. Some Critical Aspects of Closeout • Don’t forget to ask for a referral from your client. • Make sure this is a routine event at the closeout of every project. • Get the referral on the client’s official letterhead, signed by the most senior manager possible. • Remember, you can always say you did something, but having it in writing from your client is proof you did. • Plan your project completion party at the start of the project. • Successful project teams start by planning for success, then they execute the plan. • If the project schedule indicates the completion party as a separate milestone, the team is looking forward to success. • Make sure you allocate budget to make it happen.

  15. Key Elements • Completion and closeout of any contractual agreements with suppliers or providers • Formalizing customer acceptance • Closeout of any financial matters • Preparation of the project’s final performance report • Conducting a project review • Documenting lessons learned • Completing, collecting and archiving project records • Celebrating project success.

More Related