1 / 22

Risk of Error on 2000-06 Closure Ljubljana, 12-13 October 2009

Risk of Error on 2000-06 Closure Ljubljana, 12-13 October 2009. Graeme Waterhouse ESF Audit Authority for England & Gibraltar Risk Assurance Division Department for Work & Pensions. Introduction. Our experience of trying to shut the 2000-06 programmes.

davis
Download Presentation

Risk of Error on 2000-06 Closure Ljubljana, 12-13 October 2009

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Risk of Error on 2000-06 Closure Ljubljana, 12-13 October 2009 Graeme Waterhouse ESF Audit Authority for England & Gibraltar Risk Assurance Division Department for Work & Pensions Ljubljana, 12-13 October 2009

  2. Introduction Our experience of trying to shut the 2000-06 programmes. How we will communicate to the Commission: • Frequency of error • Materiality • Whether there is a high/low frequency of error • Financial impact Ljubljana, 12-13 October 2009

  3. Background • 12 programmes to shut in England & Gibraltar by 31 March 2010 • ESF is delivered by the Department for Work & Pensions • De-centralised system – delivery and A10 checks through 9 regional Government Offices Central coordinating bodies: • Managing Authority in ESF Division • Paying Authority in ESF Division • Risk Assurance Division (for A10 & A15) Ljubljana, 12-13 October 2009

  4. Approach • Apply the Commission’s Guidelines on the Closure of Assistance for 2000-06 • Apply professional standards • Explore options • Minimise any potential financial damage • Keep it simple Ljubljana, 12-13 October 2009

  5. Guidance Low frequency = “financial implications fall below a level of materiality considered appropriate by the independent body” High frequency = “confidence in entire management system is seriously affected and therefore no opinion can be given. To determine frequency a distinction must be drawn between the different categories of error”. Materiality = “The materiality level should generally not exceed 2% in order to be consistent with the methodology of the ECA. Specific justification should be provided in case a higher level is applied”. If high we must estimate the financial impact Ljubljana, 12-13 October 2009

  6. Frequency of Error Article 10 Purpose: To provide an independent assessment of the effectiveness of the management and control systems operated by the Managing Authority & Implementing Bodies for European Structural Funds Ljubljana, 12-13 October 2009

  7. Frequency of Error CALCULATE TWO ERROR RATES Programme Error Rate: • Error that exists in the Managing Authority’s control environment • Before any audit intervention • Includes results of random & risk-based Article 10 checks & other Community & national controls. • Cannot be used for extrapolation Representative Error Rate: • Based on randomly selected Article 10 controls • Can be used for extrapolation Ljubljana, 12-13 October 2009

  8. Programme Error Rate 10% x (40/500) Representative of the unchecked population Ljubljana, 12-13 October 2009

  9. Programme Error Rate Conclusion. • The programme error rate is 3.25% Ljubljana, 12-13 October 2009

  10. Representative Error Rate Based on randomly selected Article 10 checks only. Representative: • Geographic spread • Time (annual coverage) • Type/size • Measure • Randomly selected Can be used for extrapolation as it reflects the error that exists in the unchecked population Ljubljana, 12-13 October 2009

  11. Representative Error Rate Ljubljana, 12-13 October 2009

  12. Representative Error Rate Conclusion. • The representative error rate is 2.5% Ljubljana, 12-13 October 2009

  13. Materiality Materiality = “The materiality level should generally not exceed 2% in order to be consistent with the methodology of the ECA. Specific justification should be provided in case a higher level is applied”. Conclusion: • The level of error in the programme is material if the value of errors remaining in the claim exceeds 2% of the final claim value (total population) Ljubljana, 12-13 October 2009

  14. Financial Impact The checked population has already been corrected so no error remains The value of error in the Final Claim Are the errors in the final claim material? Ljubljana, 12-13 October 2009

  15. Conclusions • The programme error rate is 3.25% • The representative error rate is 2.5% • The value of the errors that remain in the final claim is within the Commission’s 2% materiality level Conclusion – there is a low frequency of error Ljubljana, 12-13 October 2009

  16. Another Example The checked population has already been corrected so no error remains The value of error in the Final Claim Are the errors in the final claim material? Ljubljana, 12-13 October 2009

  17. Conclusions • The representative error rate is 3.5% • The value of the errors that remain in the final claim exceeds the Commission’s 2% materiality level Conclusion – there is a high frequency of error Ljubljana, 12-13 October 2009

  18. Other Considerations • Stratifying the population? • Unrepresentative Samples • Off-Setting Ljubljana, 12-13 October 2009

  19. Stratifying • Basis of stratification must be set from the start of the programme • Different strata types give different overall results • Consistency across programmes • Sample sizes often too small Ljubljana, 12-13 October 2009

  20. Unrepresentative Samples Our definition: • An Article 10 check where the audit trail is completely lost (100% error) as a result of insolvency or natural disaster (fire/flood). Implication: • These can be removed from error rate and financial impact calculations Assumptions: • These are circumstances beyond the Managing Authority’s control • The audit trail did exist at the time the project operated and the likely level of error is in line with the representative error rate. Ljubljana, 12-13 October 2009

  21. Off-Setting Off –setting of positive and negative financial impacts Argument: • Commission may make corrections based on the Article 15 body’s estimated financial impact • The corrections should take account of the Managing Authority's control environment as a whole (i.e. across all programmes) Ljubljana, 12-13 October 2009

  22. Thank you for your attention! Email: graeme.waterhouse1@dwp.gsi.gov.uk Tel: (0044)113 2324777 Ljubljana, 12-13 October 2009

More Related