Midwest ISO Market Readiness Update

Midwest ISO Market Readiness Update. October 27, 2004. Seams Agreements. Created “Safe Operation Mode” with PJM Response to lessons learned during AEP and DPL integration Provides framework for efficient management of all seams Agreements with MAPP, SPP and TVA expected in December

decima
Download Presentation

Midwest ISO Market Readiness Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Midwest ISO Market Readiness Update October 27, 2004

  2. Seams Agreements • Created “Safe Operation Mode” with PJM • Response to lessons learned during AEP and DPL integration • Provides framework for efficient management of all seams • Agreements with MAPP, SPP and TVA expected in December • MAPP, SPP and MISO working together to achieve a consistent congestion management process

  3. Parallel Operations I • Parallel Operations Phase I is intended to simulate an end-to-end market experience • Internal capability testing in progress • Market Participant Interaction scheduled for November 8 through December 17 • Participants submit day-ahead and real-time bids/offers and schedules and reliability commitment offers

  4. Parallel Operations I, cont. • Clear day-ahead and real-time markets • Provide LMP data, unit commitment and schedules to participants • Bind constraints to relieve congestion • Produce daily settlement statements and weekly invoices

  5. System Operations and Parallel Operations II • During System Operations, Midwest ISO will send target basepoints and Net Schedule Interchange to Market Participants and Control Areas • Generators will adjust generation levels in response • Tests are scheduled for December • Parallel Operations Phase II, scheduled for January 3rd through 30th, will test FERC GFA and JOA functionality • Final system integration scheduled for February

  6. Participant Readiness • 76% of eligible Market Participants participated in some aspect of Day in the Life Enhanced Market Trials • 53% of Control Areas have completed open and closed loop tests • An additional 32% of Control Areas are expected to complete testing prior to the start Parallel Operations I • The remaining 15% are expected to complete testing during Parallel Operations I

  7. Stakeholder Participation • Twelve items recently identified to increase stakeholder participation including • Reach out and create targeted training for smaller market participants • Include stakeholder personnel in MISO control room during Parallel Operations • Involve stakeholders in simulator training • Provide forum for additional interaction with Readiness Advisor on metrics

  8. Regional Operating Model • Footprint Oversight Team will be responsible for • Centralized system-wide dispatch • Seams management • Overall control of the MISO footprint • Remaining reliability coordinators and generation dispatchers assigned in teams to one of three discrete regions in order to • Increase in-depth knowledge of footprint • Provide better customer service