80 likes | 96 Views
This schedule outlines the critical path for the installation and testing of the FEE PPS hardware and cable plant, including cold and hot checkout procedures. It also includes the status of reviews and upcoming acceptance tests.
E N D
FEE PPS Status Enzo Carrone June 8, 2009
Critical Path “Enhanced” QA/QC activities
FEE PPS Cold Checkout • Cold Checkout • Verifies Hardware and Cable Plant is installed and wired correctly • Verifies No Ground Shorts in the Cable Plant • EEIP Hardware and Racks • 95% Complete
FEE PPS Hot Checkout • Hot Checkout • Verifies Functionality of Hardware, Devices, and PLCs • Hi-Pot Cable Plant • Invasive to LCLS Undulator Complex Operations (2-3 Hours)
PPS Review Status • Final Design Review #2 (April 22, 2009) • Initial Acceptance Test Review • Internal Review (May 15, 2009) - Complete • External Review (near completion)
FEE Initial Acceptance Test Schedule • IAT Validation • June 17 – June 19 • Invasive to Upstream LCLS Operations • IAT Certification • June 22 - June 26 • Invasive to Upstream LCLS Operations