MuTrig-FEE Status. RIKEN/RBRC Itaru Nakagawa. Install Status. ADTX Boards & ADTX-FEE Cables All Installed Pluming St-2, Oct-7 St-3, Oct-7 3 more chassis to go To be done by today or tomorrow. Station-2 Cross Talk Measurement. Date : 30 Sep 2009 Source : 90Sr
E N D
MuTrig-FEE Status RIKEN/RBRC Itaru Nakagawa
Install Status • ADTX Boards & ADTX-FEE Cables • All Installed • Pluming • St-2, Oct-7 • St-3, Oct-7 3 more chassis to go • To be done by today or tomorrow
Station-2 Cross Talk Measurement Date : 30 Sep 2009 Source : 90Sr Source Position : Radial 90~130cm Azimuthal 20~35cm Probing point : St.2 Oct.6 Gap 3 ATDX Chs.1,2 Oct.5 St.2 20cm 1 2 Strip # 90Sr ・・・ 3 35cm 90cm~130cm Oct.7 Oct.6 (View from St.3)
Effect of Terminator • Superposition of cross • talk and Signal from • source (cross talk ~10mV) • No anode wire on • Strip# 1,4 • Terminator reduce • cross talk by ~30% (MAX) Strip# 59
Station-1 Octant-5 Re-Capacitation capacitors 2 anode cards 32 anode wires Terminator Registers
TLD badges to be installed • St-1 beam pipe shielding optimization is onging
MRG & DCMIF installation • South cable install is finished • MRG ID from DCMIF is correct • ADTX send correct data to MRG • check except Oct.7, 8 • ADTX ID check is to be done
October Schedule Noise Hunting, St-1 Recap. RSC 2nd Round Miscabling/performance Checks. American&Japanese Physics Society Joint Meeting 3rd. (Final) Round Miscabling/performance Checks. OASys Camera Alignments St-2&3 Scaffold Disassembly St-1 Scaffold Disassembly