MuTrig-FEE Install Status. RIKEN/RBRC Itaru Nakagawa. MuTRIG-FEE Install (Station-1). Completed Oct. 27. Station-2&3 Installation. Completed by Oct.29. ADTX Installation Check List. Miscabling Visible inspection Gap-by-Gap calibration logic/mask check ADTX Performance
E N D
MuTrig-FEE Install Status RIKEN/RBRC Itaru Nakagawa
MuTRIG-FEE Install (Station-1) Completed Oct. 27
Station-2&3 Installation Completed by Oct.29
ADTX Installation Check List • Miscabling • Visible inspection • Gap-by-Gap calibration logic/mask check • ADTX Performance • Dead (single) channel check • Board ID check • Slow control (threshould 10mV, 30mV) • PROM erase and Download • Efficiency • Fake hit • Timing • MuTR FEE Performance • Noise w/o HV • HV upto 1500V (st-1), 50V (st-2&3) w/ Ar-CO2 gas • Minor Tweak of Cable to improve noise • Noise w/ HV on • Gap-by-Gap calibration found one miscabling in St-1, Oct.5 • Gain stereo ~ 1, non-stereo~0.9 • LV • Miscabling • LV measurement at Chassis with all other power on
Csplit = 100pF Csplit = 30pF w/o ADboard ○ MuTR Resolution vs. Noise Achieved : 200 ~300um Intrinsic 100um Pedestal RMS/MIP
MuTR Pedestal RMS Distributionbefore/after ADTX Install Typical Pedestal RMS Distribution of MuTR Pedestal RMS Strip Number
Gap-1 Gap-2 Gap-3 MuTR Pedestal Station-1 Oct.1 Oct.2 Oct.3 Run9 Oct.4 Present Oct.5 Oct.6 Oct.7 Oct.8 stereo Non-stereo stereo Non-stereo stereo Non-stereo
Station-3 Octant-2 Noise after before
Station-3 Aluminum Foil Effect w/o foil w/ foil
MuTrig Performance • With Calibration Pulse • Timing • Efficiency • Miscabling Check • Logic Test • Without Calibration Pulse • Fake hit rates
ADTX Timing (Gap-1) Strip# Strip# Strip# Strip#
ADTX Efficiency (Gap-1) 1 efficiency 1 efficiency 1 efficiency Strip# Strip# Strip# Strip#
LL1 Trigger Readiness LL1 Board • Communication test • LL1 Board Production by end of October • ADTX - MRG - LL1 - GL1 chain test this November. • New high momentum trigger will be operated in Run10 for commissioning MuTRG-MRG Boards
DCM For Run10 Operation, 2 more FE3 were obtained from : FOCAL Colorado
Re-Capacitation Station-1 Station-2
Summary • Installation to South Arm is completed.