1 / 16

5 th IAEA Technical Meeting on ECRH Gandhinagar – 18-20 February 2009

5 th IAEA Technical Meeting on ECRH Gandhinagar – 18-20 February 2009. Fluid dynamics and thermal analysis For the ITER ECH Upper Launcher. A. Vaccaro a , R. Heidinger a , W. Leonhardt b , A. Meier a , D. Mellein b , T. Scherer a , A.Serikov c , P. Späh a , D. Strauß a

ellery
Download Presentation

5 th IAEA Technical Meeting on ECRH Gandhinagar – 18-20 February 2009

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 5th IAEA Technical Meeting on ECRHGandhinagar – 18-20 February 2009 Fluid dynamics and thermal analysis For the ITER ECH Upper Launcher A. Vaccaroa, R. Heidingera, W. Leonhardtb, A. Meiera, D. Melleinb, T. Scherera, A.Serikovc, P. Späha, D. Straußa Forschungszentrum Karlsruhe, Association FZK-Euratom a) Institute for Materials Research b) Institute for Pulsed Power and Microwave Technology c) Institute for Reactor Safety

  2. Support Flange Socket Main structure Flange connection BSM Launcher Back-end Closure Plate Main Frame The Upper Launcher in ITER

  3. The Blanket Shield Module in the UPP Front flange Rear flange Bolts are used to connect the Blanket Shield Module to the mainframe of the UPP

  4. Modelling Overview Mech. Loads Thermal Loads EM Analysis (FEM) CFD Analysis (MCNP+Finite diff.)

  5. Corner prototype and LHT facility Graphite paint The corner prototype is installed in the Launcher Handling Test facility at FZK. An active circuit provides feedwater at imposed temperature, pressure and mass flow rate. Thermocouples

  6. Shock cooling experiment The prototype is heated up to 95°C. When the equilibrium is reached, water at 25°C starts flowing into the cooling channel. The temperature is monitored by the thermocouples and IR imaging. The same (ideal) event is simulated by CFD analysis. The comparison between the simulation and the experiment will provide information about the validity of the model.

  7. CFD Model – The „frozen“ approach • Constant properties are assumed. • Steady state analysis to asses the flow field and transport properties • Transient analysis performed solving only the energy equation. • Computation time reduced from 1.5 weeks to few hours

  8. Wall temperatures. Thermocouples The curves show a good prediction of the heat exchange. The delays between the curves are determined by the real trends of the inflow.

  9. Wall temperatures – IR imaging

  10. Heat loads on the corner of the BSM The model is divided into several sectors to take into account of the non-constant heat deposition in the steel and In the water (30-60%!) Volumetric heat loads range from 1.6 to 3 MW/m3

  11. Nuclear heating – Steady state study Dtwater = 11°C G = 4.5kg/s P = 138kW High values on the flange But The steady-state scenario is not realistic. The power production in ITER is pulsed.

  12. Nuclear heating – Transient study 1 The simulation is performed over 9 successive power cycles each one with 500 s power on followed by 1500 s power off.

  13. Nuclear heating – Transient study 2

  14. Nuclear heating – Transient study 2 t=0 t=250 t=500 t=1000 t=1500

  15. Outlook: extension to the complete cooling circuit Rear flange Front flange First Wall Panel By this simulation the temperature distribution in the whole connecting flanges of the BSM can be calculated. This result is needed for the design of the bolted connection.

  16. Conclusion The Blanket Shield Module in the UPP is a challenging component due to the high thermal and mechanical loads to which it is subjected. The shock-cooling experiments on the corner prototype and the CFD simulation presented in this paper are used as instrument to verify the efficacy of the cooling system. The results also show that the cooling system is able to cool efficiently the walls and the flange of the BSM, when the nuclear heat production and the pulsed operation of the ITER reactor are taken into account. Modelling is a necessary tool for the design of some key features of the UPP, like the bolted connection of the BSM and the fixation of the entire structure to the Upper Port.

More Related