110 likes | 229 Views
ANU Shutdown Status AEM meeting. Cons Gattuso 6/3/2012. NuMI Activities. Target Pile dehumidifier repairs & upgrades - 95% complete Electrical hook ups remain should be complete today or tomorrow Phase 1 of Horn 2 RAW system NoVA /ANU upgrade -100% complete
E N D
ANU Shutdown StatusAEM meeting Cons Gattuso 6/3/2012
NuMI Activities • Target Pile dehumidifier repairs & upgrades -95% complete • Electrical hook ups remain should be complete today or tomorrow • Phase 1 of Horn 2 RAW system NoVA/ANU upgrade -100% complete • New NoVA/ANU Target Pile fan cooling coil 75% complete • New cools are on order and will arrive in 6-8 weeks • Un-forseen problem with existing cools start to leak after system was being refilled. • Relocation of TP fan controls and sum box -100% complete • This move was require to open space for Raw water system upgrades • Work cell lighting & electrical service installation -90% complete • What remain is some electrical installation for decay pipe De humidifier cooling coil. • Facility drain & drip ceiling cleaning-100% complete (will need to be repeated at the end of shut down) • Complete drain cleaning in shaft area • Completed drain cleaning in the Absorber Passageway & Hall
4 NuMI Activities • Replaced Pretarget magnets Q113, Q114, & Q120 90 % Complete • Vacuum has been restored • Cable pulls are complete • Terminations and hook up will occur later this week • Pull 6 electrical cables from the shaft to new quad locations -50% complete • Complete cable pulls through the upper labyrinth • Started cables pulls in the Pre-Target area • Installed handrail above emergency walkway • Installed scaffold in PT area • Chase to be opened in week 8 (~ 2weeks from now)
Decommissioning MI/RR • Stochastic Cooling system – 100 % Complete • 101-103 • Tanks and Stands removed • 210-212 • Tanks and Stands removed • Spool piece in place • Bake setup underway • Bake Schedule for Tuesday afternoon after Service Building power outages • R22 Line - 90 % Complete • Vacuum components in line have been harvested • Instrumentation components have been harvested • BPM • Toroids • Multi Wires • Recycler Lambertson at 212 location • Waiting on spool piece will be ready this week • MI Lambertson at 221 was removed (class 2 10-100 mr/hr)
Decommissioning MI/RR • R32 Line - 25 % Complete • Vacuum components in line will need to be harvested • Instrumentation components will need to be harvested • BPM • Toroid's • Multi Wires • Lambertson removal • MI 321 location- 100 % Complete (was class 3 100-200 mr/hr) • Spool piece in its place • RR 328 location – Schedule for later this week • Correction elements 100 % Complete • Have been harvested • Already reassigned to new girders • Mirror magnet MGS-001 • Removed and relocated for future installation in the new extraction line
Decommissioning MI/RR MI-620 Region • A150 line Decommissioning - 100 % Complete • Two 2Q130 were removed from 902 and 901 location • Magnets are being reworked for NuMI beam line spares • Required the removal and reinstallation of Q618 • MI 620 Lamberstons • Two have been removed and placed in short term storage (MSB) • One Lambertson Staged for future installation at the 306 location • MI 620 wide aperture quad has been swopped out with 306 Quad • V901 C-Magnet was removed and put into viable spares pull (TPL) • 2 kickers left in the A50 alcove (class 2-3) • Replaced of NuMI stub 100 % Complete • Replaced Q111 & Q112 (3Q120 magnets Peter porch) • Reworked Stand for V109 to abate future install problems for mangets in the stub region
MI/RR RF section • MI RF system Decommissioning - 100 % Complete (Shipped to TPL for storage) • Six 2.5 MHz RF cavities were removed • One 106 MHZ RF cavity were removed • Two Barrier Bucket RF cavities were removed • MI RF system Installation/ Maintenance • RF4A cavity installation -100 % Complete • RF15A cavity installation -20% Complete • Space for cavity has been made • Cavities determined to need tunnel repairs (1 to 2 weeks/ Cavity) • We need to pull RF cavities 8 and 16 to replace bellows and flanges. • Water cooling loop work for cavities 7, 12, 13, 15, and 17
Cables Pulls/Misc. • Cable Pulls (~450 K feet of cables) • MI-50 House • BPM cables 100 % Complete • 5 days to complete – re-spooled to length • Historically ~2 week • Sextupolecables 100 % Complete • MI-40 House • BPM cables • Being staged • Pulls will start Tuesday • BPM preamp- ion clearing module removal 100 % Complete • 1 55 gallon barrel of circuit boards (mixed wasted) • 1 64 cu. ft cube of rad waste
Injection line Installation • Recycler line installation -20% complete (Stand installation/relocation process halted) • Problems encountered • Installation drawings slow to materialize • Stands placement Interferences between the two beam lines • Stands placement issues with respect to beam center line • Verify stake out marker locations • Verifying Lattice files • We have a plan……. • MI line relocation • MI Quads and PDD magnets • 60% complete • MI-14 FluorinertPiping Installation • Installed the brackets on the wall for the Fluorinert lines in the Q104 region • Relocated theFluorinert manifold from the Q400 region to the Q104 region. • All the welds, from the penetration to the end of the Fluorinert run, that is, past the gate near the Q104 region, have been completed